HomeMy WebLinkAboutRESOLUTION NO. RESOLUTION NO. 2020-46 RESOLUTION NO. 2020-46
RESOLUTION TO APPROVE CHANGE ORDER NO. I FROM PEAK
CONSTRUCTION GROUP, INC. FOR THE FAIRFAX SPORTS
COMPLEX SPLASH PAD PROJECT
WHEREAS, the City Council of Fairfax, Iowa has contracted with Peak Construction
Group, Inc. for the Fairfax Sports Complex Splash Pad project; and
WHEREAS, Hall &Hall Engineers has recommended approval of Change Order#1 as
described below.
Fairfax Splash Pad change order
Reason for Chante order;
The water table and ground conditions at Fairfax Splash pact were
unsuitable to install the sanitary and water train piping and
required stabilization stone to get a firm foundation to install utility
piping;.We also had to build a rock base for the equipment enclosure
pad. Due to water table being so high it was decided to delete the
water manhole and install a blow off assembly in its place to gain
access to witer system so it could be blown chit for winterization.,
We also have a change in special backfill quantities for the splash
pad base. Totals as follow;
Stabilization rook used is 184.85 tons @ $32 per = $5915.20 ADD
Delete water manhole J. each @) $2400 DEDucr
Additional special back-fill 1610 CY c@ $25 per CY= $4000.00 ADD
Blow off assembly 1 each @ $550.00 ADI
Stone for unstable Splash Pad base as follows;
1.5.8 tans of niaca€tarn 641 $25 per ton =$395.00 ADD,
16 tons of modified choice stone @ $20 per ton 4 $320.00 ADD
Total ]'tet change = $8780."1,0
Subtotal $8,780.20
OHP (General Contractor's 5% Mark-up) $439.01
Bond $133.68
Total $9,352.89
NOW,THEREFORE,BE IT RESOLVED,by the City Council of the City of Fairfax,
Iowa,to approve Change Order No. 1 from Peak Construction Group,Inc. for the Fairfax Sports
Complex Splash Pad project for an additional $9,352.89 making the contract amount
$340,359.93.
BE IT FURTHER RESOLVED, by the Fairfax City Council of the City of Fairfax,
Iowa, that the Mayor and City Clerk/Treasurer are hereby authorized and directed to execute
said resolution.
Passed and approved this 12th day of May, 2020.
AYES: Otto, Volk, and Wainwright
NAYS: Daly and Pacha
urnell G. Frieden, Mayor
ATTEST:
.t°
AA
°r
Cy t is Stimson, City-clerk/Treasurer
4. t
4 , vi
IN
Pg&K
CONSTRUCTION GROUP
To:Jon Larson- Hall and Hall From: Steve Oyen
Project: Fairfax Splash Pad
Date: 5/4/2020
COR: 001
Description: Extra work from sanitary and water stabilization
Contractor Sum
Bushman $8,780.20
Notes:
Subtotal $8,780.20
OHP $439.01
Bond $133.68
Total $9,352.89
Bushman Excavating, Inc.
600 Fairfax Road Fairfax, IA 52228 1319-845-2034 ( EIN: 42-1524846
Fairfax Splash Pad change order
Reason for Change order;
The water table and ground conditions at Fairfax Splash pad were
unsuitable to install the sanitary and water main piping and
required stabilization stone to get a firm foundation to install utility
piping. We also had to build a rock base for the equipment enclosure
pad. Due to water table being so high it was decided to delete the
water manhole and install a blow off assembly in its place to gain
access to water system so it could be blown out for winterization.
We also have a change in special backfill quantities for the splash
pad base. Totals as follow;
Stabilization rock used is 184.85 tons @ $32 per = $5915.20 ADD
Delete water manhole 1 each @ $2400 DEDUCT
Additional special back-fill 160 CY @ $25 per CY = $4000.00 ADD
Blow off assembly 1 each @ $550.00 ADD
Stone for unstable Splash Pad base as follows;
15.8 tons of macadam @ $25 per ton = $395.00 ADD
16 tons of modified choke stone @ $20 per ton = $320.00 ADD
Total net change = $8780.20