HomeMy WebLinkAboutRESOLUTION NO. RESOLUTION NO. 2020-51 RESOLUTION NO. 2020-51 RESOLUTION TO APPROVE CHANGE ORDER NO. 1 FROM PRELOAD, LLC FOR THE 2020 AT-GRADE WATER STORAGE TANK IMPROVEMENTS PROJECT WHEREAS, the City Council of Fairfax, Iowa has contracted with Preload, LLC for the 2020 At-Grade Water Storage Tank Improvements project; and WHEREAS, Hall&Hall Engineers has recommended approval of Change Order#1 as described below. Add 3" of choker stone over laydown area to stabilize the surface. Original Contract Amount: $ 1,103,500.00 C.0 #1 $6.347.85 Revised Contract Amount: $1;100,847.85 NOW,THEREFORE,BE IT RESOLVED,by the City Council of the City of Fairfax, Iowa,to approve Change Order No. 1 from Preload, LLC for the 2020 At-Grade Water Storage Tank Improvements project for an additional $6,347.85 making the contract amount $1,109,847.85. BE IT FURTHER RESOLVED, by the Fairfax City Council of the City of Fairfax, Iowa, that the Mayor and City Clerk/Treasurer are hereby authorized and directed to execute said resolution. Passed and approved this Stn day of June, 2020. AYES: Otto, Daly, Pacha, Volk, and Wainwright NAYS: None Burnell G. Frieden, Mayor ATTEST: ,aeoYGY„x, m y thia Stimson, City Clerk/Treasurer § Al dr HALL & HALL ENGINEERS, INC:. CHANGE ORDER NO. 1 PROJECT: 2020 At-Grade Water Storage Tank Improvements DATE: May 13, 2020 CONTRACTOR: Preload, LLC ORIGINAL CONTRACT AMOUNT: $ 1,103,500.00 CONTRACT COMPLETION DATE: August 21,2020 ITEM#1: Add 3"of choker stone over laydown area. The laydown area was surfaced with clean Macadam Stone. The clean Macadam Stone contains little to no fine aggregates to help lock the stone in place and provide a stable surface. This has caused issues getting construction traffic in and out of the site, due to rutting and displacement of the clean stone when driven on. A layer of choker aggregate, which contains fine aggregates, needs to be added to stabilize the surface. The contract documents called out"Macadam Stone"to be used on the laydown area. There was misunderstanding by the Contractor on the type and gradations of Macadam Stone to use. However, Hall &Hall agrees that the call-out in the contract documents could have been more specific. Compensation for the extra work is recommended. The attached Change Order Request submitted by the Contractor provides a detailed price breakdown for adding the 3"layer of choker stone. The total Change Order 1 amount is$6,347.85. There will be no additional working days granted for these work changes. Original Contract Amount: $ 1,103,500.00 C.O.#1 $6,347.85 Revised Contract Amount: $1,109,847.85 ALAFALAFAfff ArmArp aw Preload, LLC �, Hall& Hall Engineers, Inc. By: By: Title: EA 1A 64 Title: Project Engineer/Inspector Date: ' 4/zO Date: 5/13/20 City of airfax, Iowa Title: Date: /( 1�,C- Wire-Wound Prestressed Concrete Tanks May 12, 2020 Mr. Jon Larson Hall& Hall Engineers, Inc. 1860 Boyson Road Hiawatha, IA 52233 Reference: 2020 At-Grade Water Storage Tank Improvements City of Fairfax, IA HHEProject No.6950-19-03 Preload Project No. 20PD103 Proposed Change Order No.01 —Choker Stone over lay down area Dear Mr. Larson, Please find below our cost breakdown to perform the following additional work.- Place ork:Place 3"of choker stone over lay down area. Scheduling of work, additional backup, clarifications and breakdowns can be found within the attachments. Estimated Cost Subcontractor(Re: Schrader Excavating Quote) $ 6,285.00 Construction Management Fee(Preload agreed to waive fee for this work) $ 00.00 Subtotal $ 6,285.00 Bond Fee(1.0% of$6,285.00) $ 62.85 TOTAL COST OF PCO No.01.......................................................... $ 6,347.85 Please provide a change order for this additional work at your earliest convenience. Thank you, Chris Lockhart Project Engineer 4000 Tower Road®Louisville, Kentucky 40219 * 125 Kennedy Drive, Suite 500® Hauppauge, New York 11788 631-231-8100® Fax 631-231-8881 ®www.preload.com 1840 Commercial Drive s PO Box 270 Walford,IA 52351 Phone: (319)845-3061 Fax: (319)845-3066 CHANGE ORDER REQUEST Job#: 20.037 COR#: 1 Start Date: 5/12/2020 Completion Date: Contractor: Preload Job Name: Above Grade Storage Tank Job Location: Fairfax Original Contract Amount: $ 148,206.10 Amount of this change in scope: $ 6,285.00 Amount of contract after change: $ 154,491.10 DESCRIPTION Place 3"of choker stone over lay down area MATERIALS LABOR QTY ITEM PRICE AMOUNT DATE HRS NAME TRADE RATE AMOUNT 375 TN Recycled Modified $ 9.00 $ 3,375.00 $ $ $ $ S - $ S - - TOTAL $ 3,375.00 $ EQUIPMENT $ CITY DESCRIPTION PRICE AMOUNT TOTAL $ 12 6109 $ 130.00 S 1,560.00 SUMMARY 15 Trucking $ 90.00 $ 1,350.00 LABOR TOTAL: $ $ MATERIALS TOTAL: $ 3,375.00 $ EQUIPMENTTOTAL: $ 2,910.00 $ TOTAL: $ 6,285.00 S $ Schrader Excavating Rep: $ $ Contractor Rep Approval: $ TOTAL S 2,910.00 Date: