HomeMy WebLinkAboutRESOLUTION NO. RESOLUTION NO. 2020-51 RESOLUTION NO. 2020-51
RESOLUTION TO APPROVE CHANGE ORDER NO. 1 FROM
PRELOAD, LLC FOR THE 2020 AT-GRADE WATER STORAGE TANK
IMPROVEMENTS PROJECT
WHEREAS, the City Council of Fairfax, Iowa has contracted with Preload, LLC for
the 2020 At-Grade Water Storage Tank Improvements project; and
WHEREAS, Hall&Hall Engineers has recommended approval of Change Order#1 as
described below.
Add 3" of choker stone over laydown area to stabilize the surface.
Original Contract Amount: $ 1,103,500.00
C.0 #1 $6.347.85
Revised Contract Amount: $1;100,847.85
NOW,THEREFORE,BE IT RESOLVED,by the City Council of the City of Fairfax,
Iowa,to approve Change Order No. 1 from Preload, LLC for the 2020 At-Grade Water Storage
Tank Improvements project for an additional $6,347.85 making the contract amount
$1,109,847.85.
BE IT FURTHER RESOLVED, by the Fairfax City Council of the City of Fairfax,
Iowa, that the Mayor and City Clerk/Treasurer are hereby authorized and directed to execute
said resolution.
Passed and approved this Stn day of June, 2020.
AYES: Otto, Daly, Pacha, Volk, and Wainwright
NAYS: None
Burnell G. Frieden, Mayor
ATTEST: ,aeoYGY„x,
m
y thia Stimson, City Clerk/Treasurer §
Al
dr
HALL & HALL ENGINEERS, INC:.
CHANGE ORDER NO. 1
PROJECT: 2020 At-Grade Water Storage Tank Improvements
DATE: May 13, 2020
CONTRACTOR: Preload, LLC
ORIGINAL
CONTRACT AMOUNT: $ 1,103,500.00
CONTRACT
COMPLETION DATE: August 21,2020
ITEM#1: Add 3"of choker stone over laydown area.
The laydown area was surfaced with clean Macadam Stone. The clean Macadam Stone contains
little to no fine aggregates to help lock the stone in place and provide a stable surface. This has
caused issues getting construction traffic in and out of the site, due to rutting and displacement of
the clean stone when driven on. A layer of choker aggregate, which contains fine aggregates,
needs to be added to stabilize the surface.
The contract documents called out"Macadam Stone"to be used on the laydown area. There
was misunderstanding by the Contractor on the type and gradations of Macadam Stone to use.
However, Hall &Hall agrees that the call-out in the contract documents could have been more
specific. Compensation for the extra work is recommended.
The attached Change Order Request submitted by the Contractor provides a detailed price
breakdown for adding the 3"layer of choker stone.
The total Change Order 1 amount is$6,347.85.
There will be no additional working days granted for these work changes.
Original Contract Amount: $ 1,103,500.00
C.O.#1 $6,347.85
Revised Contract Amount: $1,109,847.85
ALAFALAFAfff
ArmArp
aw
Preload, LLC �, Hall& Hall Engineers, Inc.
By: By:
Title: EA 1A 64 Title: Project Engineer/Inspector
Date: ' 4/zO Date: 5/13/20
City of airfax, Iowa
Title:
Date: /( 1�,C-
Wire-Wound Prestressed Concrete Tanks
May 12, 2020
Mr. Jon Larson
Hall& Hall Engineers, Inc.
1860 Boyson Road
Hiawatha, IA 52233
Reference: 2020 At-Grade Water Storage Tank Improvements
City of Fairfax, IA
HHEProject No.6950-19-03
Preload Project No. 20PD103
Proposed Change Order No.01 —Choker Stone over lay down area
Dear Mr. Larson,
Please find below our cost breakdown to perform the following additional work.-
Place
ork:Place 3"of choker stone over lay down area.
Scheduling of work, additional backup, clarifications and breakdowns can be found within the attachments.
Estimated Cost
Subcontractor(Re: Schrader Excavating Quote) $ 6,285.00
Construction Management Fee(Preload agreed to waive fee for this work) $ 00.00
Subtotal $ 6,285.00
Bond Fee(1.0% of$6,285.00) $ 62.85
TOTAL COST OF PCO No.01.......................................................... $ 6,347.85
Please provide a change order for this additional work at your earliest convenience.
Thank you,
Chris Lockhart
Project Engineer
4000 Tower Road®Louisville, Kentucky 40219 * 125 Kennedy Drive, Suite 500® Hauppauge, New York 11788
631-231-8100® Fax 631-231-8881 ®www.preload.com
1840 Commercial Drive
s PO Box 270
Walford,IA 52351
Phone: (319)845-3061
Fax: (319)845-3066
CHANGE ORDER REQUEST
Job#: 20.037 COR#: 1 Start Date: 5/12/2020 Completion Date:
Contractor: Preload Job Name: Above Grade Storage Tank
Job Location: Fairfax
Original Contract Amount: $ 148,206.10
Amount of this change in scope: $ 6,285.00
Amount of contract after change: $ 154,491.10
DESCRIPTION
Place 3"of choker stone over lay down area
MATERIALS LABOR
QTY ITEM PRICE AMOUNT DATE HRS NAME TRADE RATE AMOUNT
375 TN Recycled Modified $ 9.00 $ 3,375.00 $
$ $
$ S -
$ S -
-
TOTAL $ 3,375.00 $
EQUIPMENT $
CITY DESCRIPTION PRICE AMOUNT TOTAL $
12 6109 $ 130.00 S 1,560.00 SUMMARY
15 Trucking $ 90.00 $ 1,350.00 LABOR TOTAL: $
$ MATERIALS TOTAL: $ 3,375.00
$ EQUIPMENTTOTAL: $ 2,910.00
$ TOTAL: $ 6,285.00
S
$ Schrader Excavating Rep:
$
$ Contractor Rep Approval:
$
TOTAL S 2,910.00 Date: