HomeMy WebLinkAboutRESOLUTION NO. RESOLUTION NO. 2020-77 RESOLUTION NO. 2020-77
RESOLUTION TO APPROVE CHANGE ORDER NO. 1 FROM
KLEIMAN CONSTRUCTION FOR THE 2020 PUMP HOUSE & SITE
IMPROVEMENTS PROJECT
WHEREAS, the City Council of Fairfax, Iowa has contracted with Kleiman
Construction for the 2020 Pump House & Site Improvements project; and
WHEREAS, Hall &Hall Engineers has recommended approval of Change Order#1 as
described below.
Install four 45 degree bends on the 8" sample lines and furnish/install new fire hydrant.
Original Contract Amount: $ 2,278,183.54
4. #1 $4,606.20
Revised Contract Amount: $2,282,789.74
NOW,THEREFORE,BE IT RESOLVED,by the City Council of the City of Fairfax,
Iowa, to approve Change Order No. 1 from Kleiman Construction for the 2020 Pump House &
Site Improvements project for an additional $4,606.20 making the contract amount
$2,282,789.74.
BE IT FURTHER RESOLVED, by the Fairfax City Council of the City of Fairfax,
Iowa, that the Mayor and City Clerk/Treasurer are hereby authorized and directed to execute
said resolution.
Passed and approved this Stn day of September, 2020.
AYES: Otto, Daly, Pacha, Volk, and Wainwright
NAYS: None
urnell G. Frieden, Mayor
ATTEST: ,s stir
db
C thia Stimson, City Clerk/Treasurert
�� 8A
�� �.�A" , 6aA'4•r � _.,®hay
PROJECT: FAIRFAX SPORTS COMPLEX SPLASH PAD
DATE: September 2,2020
OWNER: City of Fairfax,Iowa
CONTRACTOR: Peak Construction Group,Inc.
ENGINEER: Hall and Hall Engineers,Inc.
CHANGE ORDER NO.2-BALANCING
SCHEDULE OF VALUES
5 Removal of Existing Sidewalk SY 1 -10.60 $ 22.40 $ 237.44
6 Borrow,Special CY -66.25 S 28.00 $ 1,855.00
35 Portland Cement Concrete Sidewalk,7" SY -11.00 $ 184.80 S 2,032.80
$ $
ORIGINAL CONTRACT AMOUNT $ 331,007.04
NET ADJUSTMENT TO ORIGINAL CONTRACT $ (4,125.24)
ORIGINAL CONTRACT WORK COMPLETED $ 326,881.80
_ SCHEDULE OF VALUES
C01 Ex=trenchde stabilization LS 1 $9,352.89 $ $9,352.89•
$
$
TOTAL NET ADJUSTMENT TO CONTRACT:
NET ADJUSTMENT TO ORIGINAL CONTRACT $ (4,125.24)
TOTAL CHANGE ORDER WORK $ 9,352.89
TOTAL CONTRACT AMENDMENT $ 5,227.65
CONTRACT SUMMARY:
ORIGINAL CONTRACT AMOUNT
$ 331,007.04
CONTRACT AMENDMENT 2-BALANCING
g 5,227.65
FINAL REVISED CONTRACT AMOUNT $ 336,234.69
OWNER: CITY OF FAIRFAX
BY:
TITLE: O c 1�•7 z—2
DATE:
CONTRACTOR: PEAK CONSTRUCTION GROUP,INC.
BY:
TITLE:
DATE:
r
ENGINEER: HALL&HALL ENGINEERS
BY: p� —
TITLE: _ Project Engineer
DATE: 9-2-2020
Page 1 of 1
HALL & HALL ENGINEERS, INC.
CHANGE ORDER NO. 1
PROJECT: 2020 Pump House & Site Improvements
DATE: September 1, 2020
CONTRACTOR: Kleiman Construction
ORIGINAL
CONTRACT AMOUNT: $ 2,278,183.54
CONTRACT
COMPLETION DATE: April 30, 2021
ITEM #1: Install four 45 degree bends on the 8" sample lines and furnish/install new
fire hydrant.
The 8" diameter samples lines will serve as a conduit for a group of smaller pipes running from
the pump house to the water storage tank. The 8" diameter sample lines originally included a 90
degree bend upon entering the pump house. It was determined that pulling these smaller pipes
through an 8" diameter 90 degree bend would be difficult, therefore, each 90 degree bend was
replaced with two 45 degree bends (four total).
The existing fire hydrant located at the northwest corner of the site near Hwy 151 was originally
intended to be removed and relocated to a different location nearby. The existing fire hydrant had
to stay in place so it could be used to throttle down the pressure in the existing main just enough
to allow the contractor to make the connection while maintaining water service to the nearby
residents. A new fire hydrant was then installed in the location where the existing hydrant was to
be relocated to. The new hydrant will allow for flushing of the new water main during the testing
and disinfection process, while the existing hydrant can remain in service for fire protection until
the new main and hydrant are allowed to be brought into service.
The attached Change Order Request submitted by the Contractor provides a detailed price
breakdown.
The total Change Order 1 amount is $4,606.20.
There will be no additional working days granted for these work changes.
Original Contract Amount: $ 2,278,183.54
C.O. #1 $4,606.20
Revised Contract Amount: $2,282,789.74
C;ML E.NGINEERINU LAND SU Z I i'ING" �./`hND. EVELC}PME.1
F .E.
H-0,1-o- f 2
I KLEIMAN CONSTRUCTION INC.
6205 LOCUSTRD.S.W.
CEDAR RAPIDS,IA 52404
DATE. 7.29.2020 CHANGE ORDER REQUEST NO.; 05
Owner: City of Fairfax _ PROJECT: Pum 11 louse and Site Inapro�e�nwnts
300 80th Street Court City of Fairfax
Fairfax IA 52228 690 Williams Blvd.
Fairfax]A 52228
A7TN: Jon Larson 'ontiih�tllcna.com, PROJECT NO: 4004 CONTRACT DATE: 4.6.2020
A CHANGE IN THE SCOPE OF WORK AND/Ott SPKIFICATIONS IS INDICATED BELOW THE OWN E:R'S PRO,\4P"t'RESPONSE IS REQUESTED
1. Description of Change:
COMM: Install 4-45 bends for sample lines. Furnish and Install new fire hydrant.
Schrader Excavating(See Attached Quotation)........................................................................ S 4,146,00
10%SUBCONTRACTORS MARK UP $ 414.60
SUBTOTAL $ 4,560.60
1%BOND PREMIUM S 45.60
TOTAL CHANGE ORDER#05 S 4,606.20
2. It is requested that the completion date be( X }unchanged( )extended by calendar days.
3. Basis of Payment:
a. { K )ADD{ )1:?IiD1JC"1'( )NO CHANGE S 4,606.20 TO/FROM the Contract Price.
b. Time and material per Contract
C. As per unit prices in Contract
d. Other basis: Lump sum
4. Additional Terms and Conditions:
a. Quoted prices are guaranteed for a period of 8 calendar days from submittal date.
b. Separate requests for time extensions will be considered valid and acceptable if no
response is received within 10 calendar days from date of submittal.
Submitted By:
Steplud L.Kleiman,President
Approved By: ¢, �. . ....:..—
Jo arson
Hall&Hall Engineers,Inc.
1840 Commercial Drive
Schraj PO Box 270
Walford, IA 52351
Phone: (319)845-3061
Fax: (319)845-3066
4
Job#: 20.054 COR#: 2 Start Date: 7/21/2020 Completion Date:
Contractor: Kleiman Construction Job Name: Fairfax Pumphouse Improvements
Job Location: Fairfax Pumphouse improvements
Current Contract Amount: $ 399,837.60
Amount of this change in scope: $ 4,146.00
Amount of contract after change: $ 403,983.60
DESCRIPTION
Install 4-45 bends for sample lines
Furnish and Install new fire hydrant j
I
I
MATERIALS LABOR
QTY ITEM PRICE AMOUNT DATE HRS INAME TRADE RATE AMOUNT
1 Fire Hydrant Assembly S 3,300.00 $ 3,300.00 2 Pipe Layer $ 65.00 $ 130.00
4 4S Bends with mega lugs $ 8S.00 $ 340.00 $
$ $
Mark up 10% $ 376.00 $ 376.00 $
TOTAL $ 4,016.00 $
EQUIPMENT $
QTY DESCRIPTION PRICE AMOUNT TOTAL $ 130.00
S SUMMARY
$ LABOR TOTAL: $ 130.00
S MATERIALS TOTAL: $ 4,016.00
S EQUIPMENT TOTAL: $ -
S TOTAL: $ 4,146.00
S -
S Schrader Excavating Rep:
S Contractor Rep Approval:
S -
TOTAL $ Date:
KLEIMAN CONSTRUCTION, INC.
6205 LOCUST RD. S.W. LETTEKOF TRATANSMIT L77
CEDAR RAPIDS, IA 52404
PH:(319) 364-8864
FX:(319) 364-6721 DATE: 9.3.2020 JOB NO.: 4002
ATTN: .Ion Lamson
TO: Hall &Hall Engtincers
RE: Hall &Hall EngAneers#6950-19-03
1860 Boyson Road City of Fairfax-•
Pump House & Site lmprorements
Hiawatha IA 52233
WE ARE SENDING YOU:
® Attached ❑ Under separate cover via the following items:
❑ Shop drmvings ❑ Prints ❑ Plans
❑ Samples ❑ Specifications ❑ Copy of letter
❑ Submittals ® ELECTRONICALLY SUBMITTED ❑
QTY
Application and Certificate for Payment AIA Document G702-August
THESE ARE TRANSMITTED as cliecked below
For approval ❑ Approved as submitted ❑ Resubmit❑ copies for approval
® For your files ❑ Approved as noted ❑ Submit ❑ copies for distribution
❑ As requested ❑ Returned for corrections ❑ Return ❑ corrected prints
❑ For review and comment ❑ PRINTS RETURNED AFTER LOAN TO US
❑ FOR BIDS DUE ® For Further Processing
REMARK:
COPY TO: City of Fairfax— SIGNED:
Pump House &Site Improvements
Ann M. Frese, Contracts A ministrator
If enclosures ate not as noted,kindly notify us at once.