HomeMy WebLinkAboutRESOLUTION NO. 2020-113 RESOLUTION NO. 2020-113
RESOLUTION TO APPROVE CHANGE ORDER NO. 5 FROM
KLEIMAN CONSTRUCTION FOR THE 2020 PUMP HOUSE & SITE
IMPROVEMENTS PROJECT
WHEREAS, the City Council of Fairfax, Iowa has contracted with Kleiman
Construction for the 2020 Pump House & Site Improvements project; and
WHEREAS, Hall&Hall Engineers has recommended approval of Change Order#5 as
described below.
Revisions to 2" water service line.
Original Contract Amount: $ 2,278,183.54
C.O.#1 (Previously Approved) $4,606.20
C.O.#2 (Previously Approved) $3,284.27
C.O. #3 (Previously Approved) $2,505.31
C.O. #4 (Previously Approved) $2,850.83
G.O. #5 $472.00
Revised Contract Amount: $2,291,902.15
NOW,THEREFORE,BE IT RESOLVED,by the City Council of the City of Fairfax,
Iowa, to approve Change Order No. 5 from Kleiman Construction for the 2020 Pump House&
Site Improvements project for an additional $472.00 making the contract amount
$2,291,902.15.
BE IT FURTHER RESOLVED, by the Fairfax City Council of the City of Fairfax,
Iowa, that the Mayor and City Clerk/Treasurer are hereby authorized and directed to execute
said resolution.
Passed and approved this 8"' day of December, 2020.
AYES: Daly, Pacha, and Wainwright
NAYS: None
ABSENT: Otto and Volk
1
Burnell G. Frieden, Mayor
gr4a
zea
ATTEST:
Cy#a Stimson, City Clerkreasurer
w
10,
HALL & HALL ENGINEERS, INC.
CHANGE ORDER NO. 5
PROJECT: 2020 Pump House&Site Improvements
DATE: December 1, 2020
CONTRACTOR: Kleiman Construction
ORIGINAL
CONTRACT AMOUNT: $2,278,183.54
CONTRACT
COMPLETION DATE: April 30, 2021
ITEM#1: Revisions to 2"water service line
The Fairfax Water Department requested changing the material of the 2"water service line from Sch.
80 PVC to Type K Copper. The addition of a curb stop valve is also required,
The attached Change Order Request submitted by the Contractor provides a detailed price
breakdown.
The total Change Order 5 amount is$472.00.
There will be no additional working days granted for these work changes.
Original Contract Amount: $2,278,183.54
C.O.#1 (Previously Approved) $4,606.20
C.O.#2(Previously Approved) $3,284.27
C.O.#3(Previously Approved) $2,505.31
C.O.#4(Previously Approved) $2,850.83
C.O.#5 $472.00
Revised Contract Amount: $2,291,902.15
Hall & Hall Engineers, Inc. City of Fairfax, Iowa
ByZ.�Z -,ef
Title: Project Engineer Title:- rte "4z"r
Date: 12/1/20 Date: ` _r� �✓
CIVIL ENGINEERING'LANDSURVEYING, 'I AND DF.VI L011MEN'I PLANNIN<3"I ANDSC:APE:ARCI91TCcC1 ME
1860 Boyson F2oad'Hiawatha, IA 52233' Ph:319.362.9548 'FAX:AX:319,362.7595
KLEIMAN CONSTRUCTION INC.
6205 Locust Rd SW
Cedar Rapids, IA 52404
Change Order Request (COR) # 1945 006 jDate : 8/3/2020
Project: City of Fairfax- Pump House &Site Improvements
300 80th ST Court Fairfax Iowa
Engineer: Hall & Hall 1860 Boyson RD, Hiawatha Iowa 52233
Attn: Bernie Frieden, Mayor, Fairfax PROJE T NO: SRF No. FS-57-20-DWSRF-005
A CHANGE IN THE SCOPE OF WORK AND/OR SPECIFICATIONS IS INDICATED BELOW.
THE OWNER'S PROMPT RESPONSE IS REQUESTED.
006
1. Description of change: COR98&ITC 006 Type K Copper Pipe
Schrader $ 425
10%Overhead & Profit for Subcontractor's Work $ 42.52
1% Bond Premium $ 4.68
Total Change Order Request $ 472.00
2. It is requested the completion date be extended by calendar days.
3. Quoted prices and terms are valid for 8 work days from submission of COR.
4.Separate requests for time extensions will be considered valid and acceptable if no response is received
within 10 calendar days from date of submittal.
Submitted by:
Matt Sattler,KCI Steve Kleiman, KCI
Approved by:
Jon Larson,Hall&Hall Bernie Frieden, Fairfax
1840 Commercial Drive
— PO Box 270
Walford, IA 52351
Phone: (319)845-3061
Fax: (319)845-3066
CHANGE ORDER REQUEST
Job#: 20.054 COR#: 3 Start Date: Completion Date:
Contractor: Kleiman Construction Job Name: Fairfax Pumphouse Improvements
Job Location: Fairfax Pumphouse Improvements
Current Contract Amount: $ 403,983.60
Amount of this change in scope: $ 425.15
Amount of contract after change: $ 404,408.75
DESCRIPTION
Install 2"copper inplace of 2" Plastic
MATERIALS LABOR
QTY ITEM PRICE AMOUNT DATE HRS NAME TRADE RATE AMOUNT
9' 2"Coper $ 8.50 $ 76.50 $
1 Curb stop $ 310.00 $ 310.00 $
Mark Up $ 38.65 $ 38.65 $
TOTAL $ 425.15 $
EQUIPMENT $
QTY DESCRIPTION PRICE AMOUNT I I I I TOTAL $
$ SUMMARY
$ LABOR TOTAL: $
$ MATERIALS TOTAL: $ 425.15
$ EQUIPMENTTOTAL: $ -
$ TOTAL: $ 425.15
$ Schrader Excavating Rep:
$ Contractor Rep Approval:
S -
TOTAL $ Date: