HomeMy WebLinkAboutRESOLUTION NO. 2006-92 Part 2 CHANGE ORDER NO. 1 PROJECT: 2006 WASTEWATER TREATMENT"PLANT IMPROVEMENTS CITY OF FAIRFAX, IOWA DATE: November 22, 2006 CONTRACTOR: KLEIIMAN CONSTRUCTION, INC. CEDAR RAPIDS, IOWA ORIGINAL CONTRACT AMOUNT: $2,065,781.D0 CONTRACT COMPLETION DATE: August 31, 2007 for begin process operation; November 1, 2007 for Contract. Liquidated damages will not apply to delays involving Section 11700—Communications and Controls. REASONS FOR ORDERING CHANGE OR EXTRA WORK: Item No. 1 change was made to simplify the revisions necessary to the existing influent structure; since this revision was only needed during the construction phase of this project, it was decided to install a temporary weir instead of aluminum stop gate. Item No. 2 change was made because the City of Fairfax will continue to use their radio telemetry alarm system for lift stations. Item No. 3 change was made because the return flow from east pond can be accomplished through the existing interconnecting lagoon cell piping. Item. No. 4 change was added due to Iowa DNR comment about needing a sludge sampling point, Item No. 5 change was added to provide for operator control of sludge pumping operations. Item No. 6 change was made at request of Fairfax Public Works Department to provide for additional storage area at the new wastewater treatment plant. Item No. 7 changes were necessary due to wiring requirements. ITEM No. 1: Delete aluminum stop gate in existing influent structure & replace with temporary plywood weir in front of new 18°outlet: Lump sum credit= ($3,100.00) less 5% 01 &P = 155.00 Subtotal = ($3,255.00) ITEM No. 2: Delete autodialer„ conduit&control wiring to Fairfax Road Lift Station: Automatic Systems credit= ($2,650.00) Ross Electric credit= ($1,625.00) less 5% O& P= (8213.75). Subtotal = ($4,488.75) ITEM No.3: Delete east pond) return pump, control panel, 2" PVC force main &wiring to pump: Automatic Systems credit= ($1,300.00) Electric Pump credit= ($500.00) Ross Electric credit= ($2,920.00) Dave Schmitt Constr. credit= ($2,408.00) less 5% O' &P = 356.40 Subtotal = ($7,484.40) ITEM No. 4: Add a 1-1/2" sampllling line from Biosolids pump valve vault to Biosolids Tank: Dave Schmitt Constr. subcontract= $1,950.00 plus 10% 0 & P= $195.00 Subtotal = $2,145.00 Change Order No. I 2006 Wastewater Treatment Plant Improvements City of Fairfax, Iowa Page 2of2 ITEM No. 5: Add float switches„ new control panel, engineering, fabrication programming & startup for Biosollds pump: Automatic Systems= $5,058.00 plus 15%10 & P = $758.70 Ross Electric subcontract= $750.00 plus 10%O & P = $75.00 Subtotal = $6,641.70 ITEM No. 6: Deleted. ITEM No. 7: Modify main service disconnect with three new lugs to accommodate extra wires, delete neutral in Publics Work Building feed & add conduit box and flex to HRU-1 for additional outside temperature sensor: Ross Electric subcontract= $341.00 plus 10% O & P $34.10 _ Subtotal = $375.10 Subtotal net change for C.O. #1 = ($6,066.35) plus bond ipremium = 0.00/ Total nate change for C.O. #1 = ($6,066.35) Original Contract Amount: $2,065,781.00 Decrease for C.O. #1 ($6,066.35 (Revised Contract Amount: $2,059,714.65 I LEIMAN CONSTRUCTION, INC. Recommended by Hall & Hall Engineers, Inc. B ' By. ' a Title: / Title:e'fJ "oz—'4 Date: Date: r' _ City of FAIRFAX, IA By: Title: Date: C � 6205 LOCUST RD. S.W. CEDAR RAPIDS,IA.52404 , DATE., 11122106 CH>UVCE ORDER Q UEET NG. i—PIECAP RE PTSED ARCHTMCT: PROJECT: 20016 Wastewater Treatment Plant Im rovemmis Miall&Hall Engineers,lne. 480Front Street 1860 Bu+'son Road Fairfax„Iowa 52220 I3awatha,Iowa 52233 PROJECT NO: ATTN' Dennis Keitel CONTRACT DATE. 6/26/06 A CHANGE IN THE SCOPE OF WORK AMID/OR SPECIFICATIONS IS INDICATED BELOW. THE OWNER'S MOMPT RESPONSE IS REQUESTED. I. Description of Change: Item, No. 1—Influent Structure: ]delete the aluminum stop plate and substitute a 1"plywood weir 31,x 396": Dave Schmitt Construction............................. DEDUCT $ 3,100.00 5% OVERHEAD&PROFIT C IEDIT: $ 155.00 T 0TAL DEMU C T f 3,255,1.0 S 2 J CF41 Item No.2—Section 11900—Controls: Delete the auto-dialer from the controls package including wiring; Automatic Systems.................................. DEDUCT $ 2,650»00 Ross Electric......................................... DEDUCT $ 1,625.00 SUBTOTAL $ 4,275,00 5%OVERHEAD&PROFIT CRED T T S 214.00 T Vit' ,JL,DEDUCT Item Na.3—Delete east pond return pump incladira$wiring,controls and 2"force main: Electric Pump........................................ LD DUCIT $ 500.00 Ross Electric......................................... DEDUCT $ 2,920.00 Automatic systems,............................ DEDUCT S 1,300.00 Dave Schmitt Construction....................... DEDUCT S 2„408.00 SUBTOTAL , EL $ 7,128.00 5%OVERHEAD&PROIFYT L'A t' S 3156.00 Iters No.4—Bio Solids Tank: Add a 1-1l2”sampling line from valve vault to bio-soPids tank: Dave Schmitt Construction....................... ADD $ 1,950.00 10%OVERHEAD&PROFIT ADD S 195.00 .0058+10%BOND PRlE10litll1M ADD S 14.00 TOTAL ADD S 2,159.00 ................... $ 2,159.00 Item°"M"1o.5—Bio-Solids Pump: Add love water cut-off ,float switchs and new control planet including euugineerisug,fabrication,programming and startup: AutomaticSystems................................. ADD S j"Os Zm Ross Electric.......................................... ADD S 75G,00 :CII 15%OVERHEAD&PROFIT ON ADD $ 759.00 10% OVERHEAD'&PROFIT ON�.0 ,ADD $ 75.00 .0058+10%BOND PRE iI0'FJ ADD $ 42.00 TOTAL ADD S 6,684.00 ................... $ 6,694.00 1Cem-No.6—South Ward: Add 6" granular surfacing at the yard area south of the cllari�e- �rs fb the-tWs ng.south access road and deGete seeding: PCT(approx 1,305'1`)..... ADD--.----S-- 16,3178.00 Delete Seeding................... ¢, .. 1JCI S - 2,11050.00 SATO 14,328.00 - o OVIEIREIE;D&PROFIT: :ON SUE WORK ADD $ .0058+10%BOND PREMIUM ADD $ T101.9 0 � � § r r' TOTAL ADD $ 15,°162.0(0 ................... $ _1062 00 Item No.7—Main service disconnect modification(additions&deletions): Ross Electric.......................................». ADD $ 341.00 10%OVERHEAD&]PROF'I'T'ADD S 34.00 .0058+10%BOND PREMIUM ADD $ 2.00 TOTALADD $ 377.00 ................... $ 377.00 TOTAL ADD TO CONTRACT $ 9,854.00 CAVDn=ends:and Sen ingsldjklLocal Settingffemporsry Intemet Fiiesl6IdK21TOR*1 RECAP Revised(2).doc EAZE. 11122106L RE cD-p AZ- q= Page 2 of 2 2. It is requested that the completion date be unchanged )extended by calendar days, 7711T'dTF 7-1 TE1770-,.- Ua;C]ai C.-I ela r&I.y Ell"C-�w'--q r e :..cFul Char',ze 0-rL.-ET-F .-'vc"'vi-.F pec .c.ur-"n f?7C'0— bc, ed' 3. Basis of Payment: x )ADD DEDUCT )NO CHANGE $ 9,854.00 TO/FROM the Contract Price. b. Time and material per Contract C. As per unit prices in Contract id, Other basis: Lump sum 4. Additional Terms and Conditions: a� Quoted prices are guaranteed for a period of 8 calendar days from submittal date. b. Separate requests for time extensions-Mll be considered valid and acceptable if no response is received within 10 calendar days from date of submittal. Submitted By: 74WAU 9, Thomas E.Kleiman,President Approved By: Dennis 1.Kcitel,P.E. William Voss,Mayor Hall&hall Engineers,Inc. City of Fair-fax CADo=nuaa end SettiugsYjkUcet Se*gBlT=poro7lntemBtFilcGlOIK21COR#I RECAP Revised(2).doc HOV-22-2003 WED 12:41 Phi KLE I iAN 00iISTRUCT I N FAX 11!3. i 3i 236+572 F, 02 . .� pQSS BLBC �INC. 710 32ND A WDATE Ord r CEDAR RAplbs, iA 52404 319-Z6-815 'E E ' NAME/AtMESS E F—Irimm coriSttuct of y a€6C+ { Color Upids,IA 52-804 i i i 9 �R PROJECT $'� ss illiggWit euro -- �RlI�TfI� TOTAL I i 375.00 abor and gist fog Ihc Pxch89,mo u i«,and inswIldon ok I)uw lugs �d odato now s��aca w and g 200, � ftommt ,� l' ie Nnci with any qu go-as, I . i Dalggo nmtr4 in pu�Ma Work B�ildi d m,--DED'I.J'CT-aft ,D A,4aiou or cvndiaiB bon cmd gom im 'I ror iddittimzI oumade to 'ox i ' i i i i This propsat wi}I be wdthdrum b y if not ampW within 58 dgy TOTAL � sQ.00 SIGNATURE w r i . is sm NOW-22-2003 -',,k D 12<-,2 F'it KL�irAM ��OS"TRUCT CIS FFl}; F°in- ,'S4372!1 06 unhlemity AVWD it/1o�nes, IP 5026&$92D 515-244-0166 L,-14ii- - 1!/Iblook - CC l7G�C7�1 wv�M.LMG;rnsur ncrs-coni E 1�.55Td3 C� RECEIVE[) voeAGti..Rm I M, V 0 D C Eooe ,, RPe Kleiman Construct�o�a Inc Invoice Data 06/22/06 6205 OCl1$t Road SW �e�voi� Me. 15'7879 cedar Rapids, 1� 5240Bill-Tei ace �;T� 3CC�I�TS i lent Gode TLET CONS InV Order WQ. 1*166442 Named In-suTed; Kleiman. Con tl"7LctiQn Inc Amount Remitted, P'iea:e return:1Pvis pcetinPt wiU't ytraf NaY116n� .. - ... iJj�tk'e chacks pmrWe lo: La Mair-Mulock-C jidon Co :���ie�r : e�rr.n .� IE�.c e 4:j• res��l �iw „ 06/22/06 06/22/06nitedFire ca-sual��l`�r �^ to �)ojjcy No D /22/07 *Nest C pact Ron.d�i Z ' .X10 1�o d issued for t e City of 'airfa. Sastowate.� ,Tretnt Plant TmproVeMentl Project. Contract'act value: to , 055,75.1 m This is a prc�v'isi 'real premium. Fn:alP remi m wildi be based on 3 7-5-0 00 '" oomph -ted contraci val'ae. 3 p 7 5Q d 00 + If you have any qte,�tions please call Joyce f Ijjerbsrt at 3 } 0 •C1 9 GG 515-2317-0103 . Th, nk yot�, U GO 5'2 5 b 3875 - . ,I S-7-5 T Tn,voice Nimber; 157$ 9 Amount Dt,le; 00 6.5 7'81 29-6 2 003 11 9-21 -02 77 JOTS Page. 1 ' q r