HomeMy WebLinkAboutRESOLUTION NO. 2006-93 Part 2 CHANGE ORDER NO. PROJECT: 2006 WASTEWATER TREATMENT PLANT IMPROVEMENTS CITY OF FAIRFAX, IOWA DATE: November 22, 2006 CONTRACTOR: KLJEIMAN CONSTRUCTION, INC. CEDAR RAPIDS, IOWA ORIGINAL CONTRACT AMOUNT: $2,065,781,00 CONTRACT COMPLETION DATE: August 31, 2007 for begin process operation; November 1, 2007 for Contract. Liquidated damages will not apply to delays involving Section 11700-Communications and Controls. REASONS FOR ORDERING CHANGE OR EXTRA WORK: Item No. 1 change was made to allow operators to remove the air diffuser lines from the Biosolids Tank without dewatering the entire tank. ITEM#1: Add lift-out cradles/brackets to each of the air diffuser Mines in the Blosolids Tank Tideflex brackets (8 brackets @$325/ea) - $2,600.00 plus 15% O & P = $390.00 Labor& Equipment= $1,300.00 plus 10%O &P = 130.00 Subtotal net change for C,O. #2 $4,420.00 plus bond premium = (0.835%x$4,420.00) := -_ 28.07 Total net change for C.Q.#2 = $4,448.07 Revised Contract Amount from. C.O.#1: $2,059,714.66 II!ncrease for C.O. #2 $4,448.07 Revised Contract Amount: $2,064,162.72 IKLEIMAN CONSTRUCTION, INC. Recommended by Hall & Hall Engineers, Inc. By - ✓ By: zU �- 'Tide: Date: �// rZO 61Date: �Z Z O ZW— City of FAIRFAX,``IA'' By: Title: Date: 1 6205 LOCUST RD, S.W. CEDAR RAPIDS,IA 52404 DATE. 11102106 CHANGE ORDER REQUESTNO.: 2 ARCHITECT: PROJECT: 2006 Wastewater Treatment Plant In2provements Hall&Hall Engineers,Inc, 480 Front Street 1860 Boyson Road Fairfax,Iowa 52228 Hiawatha,Iowa 52233 PROJECT NO: ATTN:' Dennis Keitel CONTRACT DATE: 6/26106 A C-IAP Qi'.E IN THE SCOPE OF WORK AND/OR SPE'CIPICATIONS IS INDICATED BELOW, THE OWNER'S PROMPT RESPONSE IS REQUESTED. I. Description of Change: Bio-Solids Tank: Add lift-out cradieslbraclrets to each of the air diffuser lines: Seven lines @$140.001ca. (TideBex)........................................„....................... 980.00 Labor...................................................................................................... $ 700.00 Equipment—Crane &Forklift...................................................................... $ 600.00 SUBTOTAL $ 2,,280.00 15% OVERHEAD EAIlD & PROFIT $ 342.00 2% BOND PREMIUM UM $ 52.44 TOTAL CHANGE ORDER $ 2.,674.44 2. It is requested that the completion date be( x )unchanged( _ }extended by calendar days. 3, Basis of Payment: a. ( x )A][DTD( }DEDUCT( }NO CHANGE $ 2,674.44 TO/FROM the Contract Price. b. Time and material per Contract C. As per unit prices in Contract d. Other basis: Lump sum 4. Additional Terms and Conditions: a. Quoted prices are guaranteed fora period of 8 calendar days from submittal date. b. Separate requests for time extensions will be considered valid and acceptable if no response is received within 10 calendar days from date of submittal Submitted By: �y ,f n y1 Countersigned B ° "warren W]lliarri5,Proj.M,gt% Thomas E.Kleiman, Pre t e Approved By: Dennis J.Keitel,P.E. William Voss;„Mayor Hall&hall Engineers,Inc„ City of Fairfax. \1KCISER"iPPNU!;vrENjboescnberg\Datakci\word\2620 Fairfax W O=CORMCOR#2.dec Nov. 29. 2006 9 �30AW P!O- 0060 P. 1,,� R,andy Lo l rrulzlWd Fr au: Jeffrey Kelly Ukelly@tideflex,coml Sent; Thursday, November 09, 2006 2`40 P To: 'r.IvuWleld' Subject: Fairfax, IA-Biosolids Tank Supports Randy;. reviewed our details files for a;similar style bracket and all the versions are for above the water level with locking mechanism, I reviewed the proposed bracket in reference to methods to resist movement in the dimtficn perpendicular to the tank wall and the best method wind be to use(1)of the cradle brackets (same as used with the grit tank assemblies)at the base tee of the drop pipe in addition to the mid-sectiDn bracket. The attached sketch includes views of how the drop pipe will sit within the cradle bracket. The cost per bracket including anchoring hardware is$1€15 per unit. Let me know if this method will be acceptable or whether you want to evaluate a different type of stabilizing system. Regards, Jeff Jefrey T. Felly Air Diffuser Product Manager Tidefimt Systems Engineer Tideflex"Technologies (A 12)919-0919 t.9 Ph (412)919-05 .8 Fax kel DUd&pLom At#adhed dlocuments in PDF format Can be viewed and Onted using Mobe Reader Software,available free from www.adobe.aom Atta0ed dlvoume nls in DWG format can be viewed and pAntad using Solid Works softwaro,available free fi m 17tinlht .et�Vllc4wgSjSs+n"-7_ip�eslbmduc;k�ledl;�,!�Intr eClrirAcrs.I-timl V k� e L ji FjAAA 0 ► r1 � O d 11/29/20,06 6 f ns, 29. 2006 9 , 31 AM iso, 0080 P 2 ro I a. qy 4 r 9 O R9 QMR F 4 h p Y 1719