HomeMy WebLinkAboutRESOLUTION NO. 2008-29 - CHANGE ORDER #4 TO RICKLEFS EXCAVAING RESOLUTION NO. 2008-29
RESOLUTION REGARDING CHANGE ORDER NO. 4 TO RICKLEFS
EXCAVATING,LTD FOR THE 2006 SANITARY SEWER SYSTEM
IMPROVEMENTS
WHEREAS, The City Council of Fairfax, Iowa has contracted with Ricklefs
Excavating, LTD for the 2006 Sanitary Sewer System Improvements; and
WHEREAS, Hall & ]Mall Engineers, Inc. has recommended Change Order No. 4
to Ricklefs Excavating, LTD to install 6" valve and remove and replace the existing
water main in Railroad Street.
BE IT RESOLVED,By the City Council of the City of Fairfax, Iowa, to approve
Change Order No. 4 for the 2006 Sanitary Sewer System. Improvements, which will
result in an increase of$5,528.55, as per the attached schedule.
NOW, THEREFORE, BE IT FURTHER RESOLVED, By the City Council of
the City of Fairfax, Iowa, that the Mayor and City Clerk are hereby authorized and
directed to execute said Resolution.
Passed and approved this 13th day of May, 2008.
AYES: Beer, Frieden, Magers,Rabe, Wainwright
NAYS: None
ABSENT: None
Bill Voss,Mayor
ATTEST:
Vic ie in 1, City Clerk
CHANGE ORDER NO. 4
PROJECT: 2006 SANITARY SEWER IMPROVEMENTS
CITY OF FAIRFAX, IOWA
DATE: May 5, 2008
CONTRACTOR: RIICKLEFS EXCAVATING LTD.
AN'AMOSA, IOWA
ORIGINAL
CONTRACT AMOUNT: $715,656.40
REVISED
CONTRACT AMOUNT: $775,004.40
CONTRACT
COMPLETION DATE: No Change— November 1, 2007
REASONS FOR ORDERING CHANGE OR EXTRA WORK: Install 6"valve in the water main by the
Siepman Lift Station and remove and replace the existing water main in Railroad Street,
ITEM No. 1: Install 6"valve and remove and replace the
Existing water main in Railroad Street _ $5,528.66
Total Change in Cost = $5,528.55
Revised Contract Amount(After C.O. No. 3): $775,004.40
C.O.#4 $5.528,55
Revised Contract Amount: $780,532.96
iRICKLEFS EXCAVATING, LTD. Recommended by Hall & Hall Engineers, Inc.
By: By;14LF
Title; -' tee Title; . , �
Date. Phu- , Date:
City of FAIRFAX, lA
By:
Title: r g
Date; "��� .