Loading...
HomeMy WebLinkAboutRESOLUTION NO. 2008-31 - CHANGE ORDER #6 TO RICKLEFS EXCAVATING RESOLUTION NO. 2008-31 RESOLUTION REGARDING CHANGE ORDER NO. 6 TO RICKLEFS EXCAVATING,LTD FOR THE 2006 SANITARY SEWER SYSTEM IMPROVEMENTS WHEREAS, The City Council of Fairfax, Iowa has contracted with Ricklefs Excavating, LTD for the 200^6 Sanitary Sewer System Improvements; and WHEREAS, Hall & Ball Engineers, Inc. has recommended Change Order No. 6 to Ricklefs Excavating, LTD, to construct a new top for the 'Siepman Wet Well (1 EA $776.63 EA). BE IT RESOLVED,By the City Council of the City of Fairfax, Iowa, to approve Change Order No. 6 for the 2006 Sanitary Sewer System Improvements, which will result in an increase of$776.63, as per the attached schedule. NOW, THEREFORE,BE IT FURTHER RESOLVED, By the City Council of the City of Fairfax, Iowa, that the Mayor and City Clerk are hereby authorized and directed to execute said Resolution. Passed and approved this 13th day of May, 2008. AYES: Beer, Frieden, Magers,Rabe, Wainwright NAYS: None ABSENT:None Bill Voss,Mayor ATTEST: ,J"r 8 / Vickie Kindl, City Clerk CHANGE ORDER NO. 6 PROJECT: 2006 SANITARY SEWER IMPROVEMENTS CITY OF FAIRFAX, IOWA GATE: May 5, 2008 CONTRACTOR: RIICKLEFS EXCAVATING LTD. ANAMOSA, IOWA ORIGINAL CONTRACT AMOUNT: $715,656.40 REVISED CONTRACT AMOUNT: $780,914.39 CONTRACT COMPLETION DATE: No Change—November 1, 2007 REASONS FOR ORDERING CHANGE OR EXTRA WORK: Construct a new 48" diameter concrete top with casting for the Siepman Wet Well. ITEM No. 1: Construct a new top for the Siepman Wet Well (1 EA(Q$776.63 IEA) _ $776.63 Total Change in Cost = $776.63 Revised Contract Amount (After C.O. No. 5): $780,914,39 C.O. #6 $776.63 Revised Contract Amount: _ $781,691.02 RICKLEFS EXCAVATING, LTD. Recommended by Hall & Hall Engineers, Inc. ay: By. Title: r'r r Title:1- Date: Date: City of FAIRFAX, IA Title: A ; r� Date: rP