HomeMy WebLinkAboutRESOLUTION NO. 2008-32 - CHANGE ORDER #7 TO RICKLEFS EXCAVATING RESOLUTION NO. 2008-3�2
RESOLUTION REGARDING CHANGE ORDER',NO. 7 TO RICKLEFS
EXCAVATING,LTD FOR THE 2006 SANITARY SEWER SYSTEM
IMPROVEMENTS
WHEREAS, The City Council of Fairfax, Iowa has contracted with Ricklefs
Excavating, LTD for the 2006 Sanitary Sewer System Iprovemennts; and
WHEREAS, Hall & Hall Engineers, Inc. has recommended Change Order No. 7
to Ricklefs Excavating, LTD to construct and backfill a temporary relief trench and
pumping of water (1 EA @ '$3,584.50 EA).
BE IT RESOLVED,, By the City Council of the City of Fairfax., Iowa, to approve
Change Order No. 7 for the 2006 Sanitary Sewer System Improvements, which will
result in an increase of$3,584.50, as per the attached schedule.
NOW, THEREFORE, BE IT FURTHER RESOLVED,By the City Council of
the City of Fairfax, Iowa, that the Mayor and City Clerk are hereby authorized and
directed to execute said Resolution,
Passed and approved this 13''day of May, 2008.
AYES: Beer, Frieden, Magers,Rabe, Wainwright
NAYS: None
ABSENT: None
BillVoss, Mayor
ATTEST:
� WA,P
Vickie Kindl, City Clerk
CHANGE ORDER NO. 7
PROJECT: 2006 SANITARY SEWER IMPROVEMENTS
CITY OF FAIRFAX, IOWA
DATE: May 5, 2008
CONTRACTOR: RICKLEFS EXCAVATING LTD.
ANAMOSA, IOWA
ORIGINAL
CONTRACT AMOUNT: $715,656.40
REVISED
CONTRACT AMOUNT: $7131,691.02
CONTRACT
COMPLETION DATE: No Change—November 1, 2007
REASONS FOR ORDERING CHANGE OR EXTRA WORK: Construct and backfill a temporary relief
trench and pumping of water to address the run-off from a field tile west of Fairfax Road
First 300 feet.
ITEM No. 1; Construct and backfill a temporary relief trench and
Pumping of water(1 EA Cab_$3,584.50 EA) $3,584.50
Total Change in Cost = $3,584.50
Revised Contract Amount(After C.O. No. 6): $781,691.02
C.O,#7 _.._.. 3.584,50
Revised Contract Amount: $785,275.512
RICKLEFS EXCAVATING, LTD. Recommended by Hall & Hall Engineers, Inc.
By: : By:
Title: Title:
Date: l�L " X` Zzlo� Date:
City of FAI RFAX, IA
By:
Title: ( 1
Date: _ _