HomeMy WebLinkAboutRESOLUTION NO. 2010-17RESOLUTION NO. 2010-17
RESOLUTION APPROVING CHANGE ORDER NO.8 FOR THE
WATER MAIN REPLACEMENT PROGRAM, PHASE I IMPROVEMENTS
WHEREAS, the City Council of Fairfax, Iowa has contracted with Rathje Construction
Co. for the Water Main Replacement Program, Phase I Improvements, within the corporate
limits; and
WHEREAS, Hall and Hall Engineers, Inc., has recommended approval of Change Order
No. 8, to amend the contract by accepting Item #1 as listed below for a total increase to the
contract in the amount of $2,480.34:
Item #1: Revisions to the water main configuration at the intersection of
Vanderbilt Street and Main Street, including the connection of the existing 4" and 6" water
mains to the new 8" water main, for a total increase to the contract in the amount of $2,480.34.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Fairfax,
Iowa, to approve Change Order No. 8 for the Water Main Replacement Program, Phase I
Improvements which will result in an amendment to the contract as described in the previously
listed Item #1 for a total increase to the contract in the amount of $2,480.34 to make a revised
total construction contract cost amount of $356,234.24.
BE IT FURTHER RESOLVED, by the Fairfax City Council of the City of Fairfax,
Iowa, that the Mayor and City Clerk are hereby authorized and directed to execute said
resolution.
Passed and approved this 9th day of March, 2010.
AYES: Beer, Otto, Magers, and Wainwright
NAYS: Frieden
ABSENT: None
Jaso/ Rabe, Mayor
ATTEST:
Cs ug
Cy hi Stimson, City Clerk
CHANGE ORDER NO. 8
PROJECT: WATER MAIN REPLACEMENT PROGRAM, PHASE I IMPROVEMENTS
FAIRFAX, LINN COUNTY, IOWA
DATE: February 3, 2010
CONTRACTOR: Rathje Construction Co.
Marion, Iowa
ORIGINAL
CONTRACT AMOUNT: $243,728.65
REVISED
CONTRACT AMOUNT: $353,753.90 (After C.O. #7)
MILESTONE DATE: December 9, 2009 (After C.O. #4)
REVISED CONTRACT
COMPLETION DATE: May 28, 2010 (After C.O. #4)
ITEM #1: Revisions to the water main configuration at the intersection of Vanderbilt Street and
Main Street, including the connection of the existing 4" and 6" water mains to the new
8" water main, for a total increase to the contract in the amount of $2,480.34.
ITEM
ITEM DESCRIPTION
ESTIMATED
UNIT
UNIT PRICE
(Bid
EXTENDED
NO.
QUANTITIES
Numbers)
COST
Revisions to the water main configuration
at the intersection of Vanderbilt Street and
C08-1
Main Street, including the connection of the
1
LS
$2,480.34
$2,480.34
existing 4" and 6" water mains to the new
8" water main
TOTAL: $2,480.34
Revised Contract Amount after C.O. #7
Revised Contract Amount:
Rathjee Constructi/on% Co.
By. C. ®t`t l-�`� r-- i /
t 17L-
-Title: 7L
Date:
City of Fairfax, Iowa
By: L.
Title: ro.�
Date:
Hall & Hall Engineers, Inc.
By: �4�j'
Title:
Date:= z4�L'®sr a
$353,753.90
$356,234.24