HomeMy WebLinkAboutRESOLUTION NO. 2011-62
RESOLUTION NO. 2011-62
RESOLUTION APPROVING CHANGE ORDER NO. 1 FOR THE
WATER MAIN REPLACEMENT PROGRAM, PHASE III
IMPROVEMENTS
WHEREAS, The City Council of Fairfax, Iowa has contracted with Dave Schmitt
Construction Company, Inc. for the Water Main Replacement Program, Phase III Improvements,
within the corporate limits; and
WHEREAS, Hall and Hall Engineers, Inc., has recommended approval of Change Order
No. 1, for an increase to the contract amount of $50.00 as listed below:
C.O. #1, Item 1 - Adjustments to Proposed Parking Lot Improvements
Line item 11, “Subgrade Stabilization with Macadam Stone” increased 18 SY for
an increase of $26.00/SY x 18 SY = $468.00.
Line item 14, “Special Backfill for Parking Lot Surface (Asphalt Millings Rolled
into Place, 6” Thick” increased 18 SY for an increase of $5.00/SY x 18 SY =
$90.00.
Line item 42, “6” Portland Cement Concrete for Parking Lot” adjusted from an
estimated 174 SY to 156 SY, for a decrease of $44.00/SY x 18 SY = ($792.00).
Line item 48, “Car Stops (Installation in PCC and Granular Surface)” increased
by 4 for an increase in price of $71.00/Car Stop x 4 = $284.00.
The total adjusted Change Order #1 amount is an increase of $50.00
BE IT RESOLVED, by the City Council of the City of Fairfax, Iowa, to approve
Change Order No. 1 for the Water Main Replacement Program, Phase III Improvements which
will result in an increase to the contract amount of $50.00 to make a revised total construction
contract cost amount of $266,764.80.
NOW, THEREFORE, BE IT FURTHER RESOLVED, by the Fairfax City Council of
the City of Fairfax, Iowa, that the Mayor and City Clerk/Treasurer are hereby authorized and
directed to execute said resolution.
th
Passed and approved this 13 day of September, 2011.
AYES: Beer, Frieden, Otto, Magers, and Wainwright
NAYS: None
__________________________
Jason Rabe, Mayor
ATTEST:
_______________________________
Cynthia Stimson, City Clerk/Treasurer