HomeMy WebLinkAboutRESOLUTION NO. 2011-74 RESOLUTION NO. 2011-74
• RESOLUTION APPROVING CHANGE ORDER NO. 2 FOR THE
WATER MAIN REPLACEMENT PROGRAM, PHASE III
IMPROVEMENTS
WHEREAS, The City Council of Fairfax, Iowa has contracted with Dave Schmitt
Construction Company, Inc. for the Water Main Replacement Program, Phase III Improvements,
within the corporate limits; and
WHEREAS, Hall and Hall Engineers, Inc., has recommended approval of Change Order
No. 2, for an increase to the contract amount of$5,688.00 as listed below:
ITEM#1: Adjustments to Water Main Alignment and Installation
The existing water main is located approximately 4 feet east of where it was originally thought.
It is therefore in the way of the proposed water main alignment. Engineering deemed it most
feasible to move the proposed water main alignment 4 feet farther east. In doing so, 3 power
poles and 2 trees become very close to the proposed water main trench and will require shoring
and possible tree trimming. The method of pipe installation has also changed so that water main
installation will begin at the north on Fairfax Road and continue south to a point beyond the
existing water main. This change was made so that water service could be maintained to the
residents on the east side of Fairfax Road while reducing the risk of a blowout at the existing
water main bend near Fairfax Road and Linn Street during the proposed water main installation.
In making this change, the water main will need to be tested in different segments. The cost of
• this item is for the additional testing required for this segment, shoring and trimming of trees.
Total cost for this item is $1,260.00, as reflected in the attached Change Order 2 Request#1 from
Dave Schmitt Construction.
ITEM#2: Plug Bushman Valve
An additional valve was installed to the south of the T at the intersection of Fairfax Road and
Linn Street. Daniel Bushman provided this valve, at no cost to the city to ease future
connections to his property and properties to the south. This item is for a plug on the
downstream end of this valve to ensure that the valve is not errantly opened with no water main
connection present to the south. The total amount of this item is $350.00, as reflected in the
attached Change Order 2 Request#2 from Dave Schmitt Construction.
ITEM#3: Boring under Fairfax Road
The decision was made to bore the water main under Fairfax Road at the intersection of Linn
Street. The reason for this change was so that no Sealcoat pavement would have to be removed
and replaced and Fairfax Road would not have to be shut down. The cost of this item is for the
change of the water main material and additional equipment mobilization required to perform
this work. The total amount of this item is $1,023.00, as reflected in the attached Change Order
2 Request #3 from Dave Schmitt Construction. Because of this work, the 6" Asphalt over 6"
Granular Subbase needed to patch Fairfax Road (Line Item #43) will not be necessary. This is
an approximately $2,400 bid item that should not be necessary as a result of this change.
1110
ITEM#4: Sitework
Dave Schmitt Construction placed the spoils of the water main excavation along Linn Street to
the south along the existing asphalt millings trail. This area was chosen instead of placing it on
• Linn Street and the adjacent ditch slope due to the wetness of the excavated material and the
narrowness of Linn Street. While this made it impossible to save the existing trail, it saved 3
weeks of road closure on Linn Street and preserved the sealcoat road and grass slope along the
road, which are always problem areas on every project. The cost of this item is to replace the
part of the disturbed trail that will not be constructed as PCC pavement in the spring as a part of
the Murphy Ball Fields project. The total cost for this item is $3,020.00, as reflected in the
attached Change Order 2 Request#4 from Dave Schmitt Construction.
The total Change Order 2 amount is an addition of$5,688.00
Original Contract Amount: $266,714.80
C.O. #1 $50.00
C.O. #2 $5,688.00
Revised Contract Amount: $272,452.80
BE IT RESOLVED, by the City Council of the City of Fairfax, Iowa, to approve
Change Order No. 2 for the Water Main Replacement Program, Phase III Improvements which
will result in an increase to the contract amount of$5,688.00 to make a revised total construction
contract cost amount of$272,452.80.
NOW, THEREFORE, BE IT FURTHER RESOLVED, by the Fairfax City Council of
• the City of Fairfax, Iowa, that the Mayor and City Clerk/Treasurer are hereby authorized and
directed to execute said resolution.
Passed and approved this 11th day of October, 2011.
AYES: Beer, Frieden, Otto, and Magers
NAYS: None.
ABSTENTION: Wainwright
Jason abe, Mayor
ATTEST:
CA141'eta"
Kathy Everett, Deputy City Clerk
•
CHANGE ORDER NO. 2
PROJECT: PHASE III WATER MAIN REPLACEMENT IMPROVEMENTS
DATE: September 29, 2011
CONTRACTOR: Dave Schmitt Construction Company, Inc.
Cedar Rapids, Iowa
ORIGINAL
CONTRACT AMOUNT: $ 266,714.80
ORIGINAL CONTRACT
COMPLETION DATE: 60 Working Days from September 12, 2011
ITEM #1: Adjustments to Water Main Alignment and Installation
The existing water main is located approximately 4 feet east of where it was originally thought. It is
therefore in the way of the proposed water main alignment. Engineering deemed it most feasible to move
the proposed water main alignment 4 feet farther east. In doing so, 3 power poles and 2 trees become
very close to the proposed water main trench and will require shoring and possible tree trimming. The
method of pipe installation has also changed so that water main installation will begin at the north on
Fairfax Road and continue south to a point beyond the existing water main. This change was made so
that water service could be maintained to the residents on the east side of Fairfax Road while reducing
the risk of a blowout at the existing water main bend near Fairfax Road and Linn Street during the
proposed water main installation. In making this change, the water main will need to be tested in different
• segments. The cost of this item is for the additional testing required for this segment, shoring and
trimming of trees. Total cost for this item is $1,260.00, as reflected in the attached Change Order 2
Request#1 from Dave Schmitt Construction.
ITEM #2: Plug Bushman Valve
An additional valve was installed to the south of the T at the intersection of Fairfax Road and Linn Street.
Daniel Bushman provided this valve, at no cost to the city to ease future connections to his property and
properties to the south. This item is for a plug on the downstream end of this valve to ensure that the
valve is not errantly opened with no water main connection present to the south. The total amount of this
item is $350.00, as reflected in the attached Change Order 2 Request#2 from Dave Schmitt
Construction.
ITEM #3: Boring under Fairfax Road
The decision was made to bore the water main under Fairfax Road at the intersection of Linn Street. The
reason for this change was so that no Sealcoat pavement would have to be removed and replaced and
Fairfax Road would not have to be shut down. The cost of this item is for the change of the water main
material and additional equipment mobilization required to perform this work. The total amount of this
item is $1,023.00, as reflected in the attached Change Order 2 Request#3 from Dave Schmitt
Construction. Because of this work, the 6" Asphalt over 6" Granular Subbase needed to patch Fairfax
Road (Line Item #43)will not be necessary. This is an approximately$2,400 bid item that should not be
necessary as a result of this change.
ITEM #4: Sitework
• Dave Schmitt Construction placed the spoils of the water main excavation along Linn Street to the south
along the existing asphalt millings trail. This area was chosen instead of placing it on Linn Street and the
adjacent ditch slope due to the wetness of the excavated material and the narrowness of Linn Street.
While this made it impossible to save the existing trail, it saved 3 weeks of road closure on Linn Street
and preserved the sealcoat road and grass slope along the road, which are always problem areas on
• every project. The cost of this item is to replace the part of the disturbed trail that will not be
constructed as PCC pavement in the spring as a part of the Murphy Ball Fields project. The total cost for
this item is $3,020.00, as reflected in the attached Change Order 2 Request#4 from Dave Schmitt
Construction.
The total Change Order 2 amount is $5,688.00
Original Contract Amount: $266,714.80
C.O. #1 $50.00
C.O. #2 $5,688.00
Revised Contract Amount: $272,452.80
Dave Schmitt Construction Company, Inc. Hall & Hall Engineer nc.
By: blvk ti, By: _
Title: V!>.�L* 19/ Title: 60..4l n wcnwr
Date: te..t . �J, I ( Date: to /3 /
City of Fairfax, Iowa
By: 9/1"114
• Title: iinafor
Date: /0)(L/6
S
•
SEWER • TRUCKING • EXCAVATION
CONSTRUCTION CO INC. WATER • DEMOLITION • GRADING
250 50TH AVE.S.W,CEDAR Rams,IOWA 52404 (319)365-8669 FAx(319)365-2677 EQUAL OPPORTUNITY EMPLOYER
CHANGER ORDER #1-MOVE WATER MAIN ALIGNMENT
From: DAVE SCHMITT CONSTRUCTION Project: 11-0832BH
250 50TH AVE S.W. Description: FAIRFAX WATER MAIN CHANGE
CEDAR RAPIDS, IA 52404 ORDER #1
Phone: 319-365-8669 Bid Date: 9-26-2011
Fax: 319-365-2677
To:
•
ITEM DESCRIPTION BID QTY U/M UNIT BID AMOUNT
01 TREE/ POLE OBSTRUCTIONS 1.000 LS 475.00 $475.00
02 ADDITIONAL TESTING 1.000 LS 785.00 $785.00
TOTAL. BID: $1,260.00
•
9/26/2011 DAVE SCHMITT CONSTRUCTION
•
climitt
SEWER • TRUCKING • EXCAVATION
=CONSTRUCTION CO ':INC WATER • DEMOLITION • GRADING
250 50TH AVE,O.W.,CEDAR RAPIDS,IOWA 52404 (319)365.8669 FAx(319)365-2677 EQUAL OPPORTUNITY EMPLOYER
CHANGER ORDER #2- PLUG BUSHMAN VALVE
From: DAVE SCHMITT CONSTRUCTION Project: 11-0833BH
250 50TH AVE S.W. Description: FARIFAX WATER MAIN CHANGE
CEDAR RAPIDS, IA 52404 ORDER#2
Phone: 319-365-8669 Bid Date: 9-26-2011
Fax: 319-365-2677
To:
ITEM DESCRIPTION BID QTY U/M UNIT BID AMOUNT
01 PLUG BUSHMAN VALVE 1.000 LS 385.00 $385.00
TOTAL BID: $385.00
9/26/2011 DAVE SCHMITT CONSTRUCTION
• (sc,;(-.1144.4,,
) 7atte _hmit t
SEWER ° TRUCKING • EXCAVATION
=CONSTRUCTIONZO._ZNC. WATER • DEMOLITION ° GRADING
250 50TH AVE.S.W., CEDAR RAPIDS,IOWA 52404 (319)365-8669 FAX(319)386-2677 EQUAL OPPORTUNITY EMPLOYER
CHANGE ORDER #3- BORE UNDER FAIRFAX RD.
From: DAVE SCHMITT CONSTRUCTION Project: 11-0834BH
250 50TH AVE S.W. Description: FAIRFAX WATER MAIN- CHANGE
CEDAR RAPIDS, IA 52404 ORDER #3
Phone: 319-365-8669 Bid Date: 9-26-2011
Fax: 319-365-2677
To:
•
ITEM DESCRIPTION BID QTY U/M UNIT BID AMOUNT
01 BORING MATERIAL CHANGE 60.000 LF 4.40 $264.00
02 BORING 60.000 LF 12.65 $759.00
TOTAL BID: $1,023.00
I
i
• i
9/27/2011 DAVE SCHMITT CONSTRUCTION
• 4(.0f �X0,3 h (y out��eF�
SEWER ° TRUCKING ° EXCAVATION
:CONSTRUCTION CO. INC. WATER ° DEMOLITION 6 GRADING
250 50TE AVE. S.W,CEDAR RAPIDS,IOWA 52404 (319)365.8669 FAX(319)365-2677 EQUAL OPPORTUNITY EMPLOYER
Proposal: Sitework CiAmGc enol-.
From: Dave Schmitt Construction Co. Inc. Project: A11-157PEM
250 50th Avenue SW Description: Fairfax Trail Repair
Cedar Rapids, IA 52404 Bid Location: Fairfax, IA
Phone: (319) 365-8669 Bid Date: September 28, 2011
Fax: (319) 365-2677
To: City of Fairfax
40
ITEM I DESCRIPTION BID QTY U!M UNIT BID AMOUNT
01 755.000 SY 1.00 $755.00
SUBGRADE PREPARATION
02 755.000 SY 1.00 $755.00
GEOTEXTILE
03 755.000 SY 2.00 $1,510.00
SPECIAL BACKFILL FOR TRAIL SURFACE (ASPHALT
MILLINGS 2" THICK)
TOTAL BID: $3,020.00
•
Dave Schmitt Construction Co. Inc.