HomeMy WebLinkAboutRESOLUTION NO. 2013-55 RESOLUTION NO. 2013-515
RESOLUTION TO APPROVE CIIANGE ORDER ER NO. l FROM
RIC KL.EFS EXCAVATING, LTD. FOR THE PHASE .1, EAST
CEMETERY .ROAM RECONSTRUCTION, DRAINAGE, STORM
SEWER, WATER MAIN, AND SANITARY SEWER
IMPROVEMENTS PROTECT
WHEREAS, the City Council of Fairfax, Iowa has contracted with Ricklefs
Excavating, Ltd. for the Phase 1 East Cemetery Road Reconstruction, Drainage, Storm
Sewer, Water Main, and Sanitary Sewer Improvements Project, within the corporate
limits; and
WI�.+RE,AS, Mall and Mall. Engineers, Inc:., has recommended alaproval of
Change Order No. 1 from Ricklefs Excavating, Ltd. The current contract amount is
$1,411,555.00. This Change Order No. 1 is a deduction to the contract amount of
$94,380.90,making the new contract amount $1,317,174.10 as described below:
The following are items being adjusted and/or added to the contract, the actual total construction
cost savings will be seen with reduced quantities of various items_
ITEM #1: CHANGE IN UNIT PRICE -8" Dia. PVC Truss Sanitary Sewer Gravity Main
Due to reducing the amount of 8" Dia. PVS Truss Sanitary Sewer Gravity Main,
there is an additional cost associated with the dewatering which was spread
out over the original sanitary sewer length. This item will increase the unit
price by$11.10 per LF for the remaining sanitary sewer. New unit price with
this change is$91.10 per LF.
ITEM#2: CHANGE IN I UNIT PRICE - 24" Dia. RCP Sanitary Sewer Gravity Main
Due to reducing the amount of 24" Dia. RCP Sanitary Sewer Gravity Main,
there is an additional cost associated with the dewatering which was spread
out over the original sanitary sewer length. This item will increase the unit
price by$11.00 per LF for the remaining sanitary sewer. New Unit Price with
this change is$171.00 per LF.
ITEM #3: CHANGE IN I UNIT PRICE-24" Dia. RCP (or PVC)Sanitary Sewer Gravity
Main
The contractor requested a change in the pipe material for the 24" Dia. RCP (or
PVC) Sanitary Sewer Gravity Main to Contech A-2000, this pipe material is
acceptable per the Cedar Rapids Metropolitan Design Standards and there is a
cost savings associated with this change. This item will decrease the unit price
by$10.50 per LF. The new unit price with this change and change from Item #
2 is $160.50 per LF.
ITEM#4 ADD BID ITEM 8" Dia PVC Sanitary Sewer(C-900)- Directionally Drilled
This item is being added to directionally drill the sanitary sewer between two
residentiallots to reduce the overall sanitary sewer quantities. The unit price is
$110.00 per LIF with an estimated quantity of 365 LF.
ITEM #5 ADD BID ITEM 8" Dia PVC Water Main (C-900)-- Directionally Drilled
Under Casey's Drives
This item is being added to directionally drill the water main under the Casey's
Drives rather than using an open cut installation. The unit price is$37.29 per
LF with an estimated quantity of 300 LF.
ITEM #6 ADD BID ITEM -12" Dia PVC Water Main (C-900) Directionally Drilled
Under Tributary to Prairie Creek
This item is being added to directionally drill the water main under the tributary
to Prairie Creek rather than installing the water main in steel casing pipe. The
unit price is $60.00 per LF with an estimated quantity of 300 LF
Change Order No. is Summary of Costs
Item #1 CHANGE IN UNIT PRICE-8"Dia. PVC Truss Sanitary LF 1,141 $11.10 $12,665.10
Sewer Gravity Main
Item #2 CHANGE IN UN:IIT PRICE-24" Dia. RCP Sanitary LF 1,501 $11.00 $16,511.00
Sewer Gravity Main
CHANGE IN UNIT PRICE-24" Dia. RCP Sanitary
Item #3 Sewer Gravity Maln LF 1,501 -$10.50 -$15,760,50
Item #4 ADD BID ITEM-8"Dia PVC Sanitary Sewer(C-900)- LF 365 $110.00 $40,150.00
Directionally Drilled
Item #5 ADD BID ITEM-8" Dia PVC Water Main (C-900)-- LF 300 $37.29 $11,187,00
Directionally Drilled Under Casey's Drives
-------------- .............
ADD BID ITEM- 12" Dia PVC Water Main (C-900)
Item #6 LF 300 $60.00 $18,000,00
Directionally Drilled Under Tributary to Prairie Creek
TOTAL CHANGE ORDER No. 11 $82,752.60
Reductions in Bid Quantities Associated with Change Order#1
BID ITEM No. 9-Removal and Disposal of Existing
Deduct#1 Asphalt Pavement(East Cemetery Road and Casey's SY -77 $5.50 -$423.50
General Store Driveways
Deduct#2 BID ITEM No. 10-Removal and Disposal of Existing SY -850 $1.00 -$850.00
Seal Coat(E Cemetery Road)
Deduct#3 BID ITEM No. 18-Trench Stabilization (Contingency) CY -75 $20.00 -$1,500.00
Deduct#4 BID ITEM No. 19-Granular Backfill(Contingency) CY -1,700 $18.00 -$30,600.00
--------------------- -----------------1-1--— :
Deduct#5 BID ITEM No, 20-Boring and Jacking 20" Dia, Steel LF -70 $170.00 -$11,900.00
Casing Pipe with Installation of 12" Dia.Water Main
BID ITEM No.211 -8" Dia. PVC Truss Sanitary Sewer
Deduct#6 LF -743 $80.00 -$59,440.00
Gravity Main
Deduct#7 BID ITEM No. 22 _24" Dia. RCP Sanitary Sewer LF -189 $160.00 -$30,240.00
Gravity Main
BID ITEM No.25-Sanitary Sewer Manholes (6inside,
Deduct#8 dia.) EA -1 $3,800,00 -$3,800.00
Deduct#9 BID ITEM No. 30-18"Dia. HDPE Storm Sewer Pipe LF -90 $40,00 -$3,600.00
(Solid Dual Wall,Smooth Interior)
Deduct#10 BID ITEM No.40- 12"Dia PVC Water Main (C-900) LF -530 $31.00 $16,430,00
Deduct#11 BID ITEM No. 53-Cast-in-Place Concrete for CY -30 $200.00 -$6,000�00
Concrete Pipe Encasement
Deduct#12 BID ITEM No. 54-6"Asphalt Cement Concrete SY -200 $32.00 -$6,400,00
Driveway(Includes 6"granular Subbase)
Deduct EM No. 55-8"Gravel -Class A Road Stone SY -850___] $7.00 -$5,950.00
TOTAL DEDUCTIONS ANTICIPATED WITH CHANGE ORDER No. 1: -$177,133.50
TOTAL CHANGE ORDER No. 1 AMOUNT WITH REDUCTIONS IN BID QUANTITIES:
REVISED CONTRACT AMOUNT: L $1,317,174.101
CHANGES IN SCHEDULE:
Due to a desire to allow the farmer to remove sweet corn in the general area of the
proposed drainage swale the late start date is revised to August 19, 2013.
The Milestone Dates and Descriptions are revised as follows,.
Milestone 1: Installation and seeding complete for the drainage swale
9/18/13 including the associated 12" dia. storm sewer.
Milestone 2- The following shall be complete (installed, tested and
12118/13 operational):
• All water main along East Cemetery Road.
Water main along Williams Blvd from Sta 0+00 to Sta
8+50.
• All 24" dia. sanitary sewer.
8" dia. sanitary sewer to be directionally drilled to East
Cemetery Road and all other 8" sanitary sewer within East
Cemetery Road,
8" dia, sanitary sewer serving EIB property (as shown on
Sheet F.04 of plans).
Sanitary sewer lift station.
Milestone I All remaining work completed and entire project seeded.
5/16/13
NOW, THEREFORE, RE IT RESOLVED, by the City Council of the City, of
Fairfax, Iowa, to approve Change Order No. I from Ricklefs Excavating, Ltd. for the
Phase I East Cemetery Road Reconstruction, Drainage, Ston n Sewer, Water Main, and
Sanitary Sewer Improvements Project.
BE IT FURTHER RESOLVED, by the Fairfax City Council of the City of
Fairfax, Iowa, that the Mayor and City Clerk/Treasurer are hereby authorized and
directed to execute said resolution.
Passed and approved this 13'h day of August, 2013.
AYES. Beer, Frieden, Otto, Magers, and Wainwright
NAYS: None
Jason be, Mayor
ATTEST:
Cy Chia Stimson, City Clerk/Treasurer
C' 4.
CHANGE ORDER NO. 'I
PROJECT: PHASE I EAST CEMETERY ROAD RECONSTRUCTION, DRAINAGE, STORM
SEWER, WATER MAIN, AND SANITARY SEWER IMPROVEMENTS
DATE: August 13, 2013
CONTRACTOR: Riclklefs Excavating, Ltd
Anamosa, Iowa
ORIGINAL
CONTRACT AMOUNT: $ 1,411,555,00
ORIGINAL CONTRACT
COMPLETION DATE: 80 Working Days from August 14, 2013
GENERAL DESCRIPTION OF CHANGE ORDER:
This change order is being proposed as an effort to reduce the overall'construction cost to an amount
more in line with budgetary numbers. With Ricklefs Excavating, Ltd. being awarded the contract it
presented an opportunity to directionally drill some of the 8"diameter sanitary sewer which allows
removal of approximately 567 LF of sanitary sewer overall.
CHANGES IN BID ITEMS:
The following are items being adjusted and/or added to the contract, the actual total construction cost
savings will be seen with reduced quantities of various items.
i
ITEM #1: CHANGE IN UNIT PRICE -8" Dia.. PVC Truss Sanitary Sewer Gravity Main
Due to reducing the amount of 8" Dia. PVS Truss Sanitary Sewer Gravity Main, there is
an additional cost associated with the dewatering which was spread out over the
original sanitary sewer length. This item will increase the unit price by$11.10 per LF
for the remaining sanitary sewer. New unit price with this change is $91.10 per LF.
ITEM #2: CHANGE IN UNIT PRICE -24" Dia. RCP Sanitary Sewer Gravity Main
Due to reducing the amount of 24" Dia. RCP Sanitary Sewer Gravity Main, there is an
additional cost associated with the dewatering which was spread out over the original
sanitary sewer length. This item will increase the unit price by$11.00 per LF for the
remaining sanitary sewer. New Unit Price with this change is $171.00 per LF.
ITEM #3: CHANGE IN UNIT PRICE -24" Dia. RCP for PVC)Sanitary Sewer Gravity Main
The contractor requested a change in the pipe material for the 24" Dia.. RCP (or PVC)
Sanitary Sewer Gravity Main to Contech A-2000„ this pipe material is acceptable per
the Cedar Rapids Metropolitan Design Standards and there is a cost savings
associated with this change. This item will decrease the unit price by$10.50 per LF.
The new unit price with this change and change from Item#2 is $160.50 per LF.
ITEM #4 ADD BID ITEM-8" Dia PVC Sanitary Sewer(C-900)-Directionally Drilled
This item is being added to directionally drill the sanitary sewer between two residential
lots to reduce the overall sanitary sewer quantities. The unit price is $110.00 per LF
with an estimated quantity of 365 LF.
ITEM #5 ADD BID ITEM -8" Dia PVC Water Main (C-900) -- Directionally Drilled Under
Casey's Drives
This item is being added to directionally drill the water main under the Casey's Drives
rather than using an open cut installation. The unit price is $37.29 per LF with an
estimated quantity of 300 LF.
Page 1 of 3
ITEM#6 ADD BID ITEM -'12" Dia PVC Water Main (C-900) Directionally Drilled Under
Tributary to Prairie Creek
This item is being added to directionally drill the water main under the tributary to
Prairie Creek rather than installing the water main in steel casing pipe. The unit price is
$60.00 per LF with an estimated quantity of 300 LF.
Change Order No. 1: Summary of Costs
CHANGE IN UNIT PRICE-8" Dia. PVC Truss Sanitary
Item#1 LIF 1,141 $11,10 $12,1665.10
Sewer Gravity Main
CHANGE IN UNIT PRICE-24" Dia. RCP Sanitary
Item#2 LIF 1,501 $11'00 $16,511.00
Sewer Gravity Main
Item#3 CHANGE IN UNIT PRICE-24" Dia. RCP Sanitary Sewer Gravity Main LF 1,501 -$10.50 -$15,760.50
ADI) BID ITEM-8" Dia PVC Sanitary Sewer(C-900)-
Item#4 Directionally Drilled LF 365 $110.00 $40,150,00
ADD BID ITEM-8" Dia PVC Water Main (C-900)
Item#5LF 300 $37,29 $11,187.00
Directionally Drilled Under Casey's Drives
ADD BID ITEM- 12" Dia PVC Water Main(C-900)
Item#6 LF 300 $60.00 $18,1000.00
Directionally Drilled Under Tributary to Prairie Creek
TOTAL CHANGE ORDER No. 1: $82,75260
Reductions in Bid Quantities Associated with Change Order#1
BID ITEM No. 9- Removal and Disposal of Existing
Deduct#1 Asphalt Pavement(East Cemetery Road and Casey's SY -77 $5,50 -$423.50
General Store Driveways)
—-—------------------------.... m.,.,..
BID ITEM No. 10- Removal and Disposal of Existing
Deduct#2 SY -850 $1,00 -$851).00
Seal Coat(E Cemetery Road)
Deduct#3 BID ITEM No. 18-Trench Stabilization (Contingency) CY -� -75 $20.00 -$1,500.00
Deduct#4 BID ITEM No. 19-Granular Backfill(Contingency) CY -1,700 $18.00 -$30,600.00
BID ITEM No. 20- Boring and Jacking 20" Dia. Steel
Deduct#5 LF -70 $170.00 -$11,900.00
Casing Pipe with Installation of 12"Dia,Water Main
BID ITEM No. 21 -8"Dia. PVC Truss Sanitary Sewer
Deduct#6 LF -743 $80,00 -$59,440.00
Gravity Main
BID ITEM No. 22 -24""Dia, RCP Sanitary Sewer
Deduct#7 LF -189 $160,00 -$30,240.00
Gravity Main
BID ITEM No. 25- Sanitary Sewer Manholes(5'inside Deduct#8 dia.) EA -1 $3,800.00 -$3,800.00
----------------------- —----------------
Deduct#9 BID ITEM No. 30- 18"Dia. HDPE Storm Sewer Pipe LF -90 $40.00 -$3,600,00
(Solid Dual Wall, Smooth Interior)
Deduct#10 BID ITEM No. 40- 12"Dia.PVC Water Main (C-900) LF -530 $31.00 -$16,430.00
Deduct#11 BID ITEM No. 53-Cast-in-Place Concrete for CY -30 $200.00 -$6,1000.00
Concrete Pipe Encasement
Deduct#12 BID ITEM No. 54-6"Asphalt Cement Concrete SY -200 $32.00 -$6,400.00
Driveway(includes 6"19 ranular Subbase)
,
Deduct#13 BID ITEM No. 55-8"Gravel -Class A Road Stone SY 1 -850 $7.00 -$5,950.00
TOTAL DEDUCTIONS ANTICIPATED WITH CHANGE ORDER No. 1: -$177,133.50
TOTAL CHANGE ORDER No. 1AMOUNT WITH REDUCTIONS IN BID QUANTITIES: 350.90
.
REVISED CONTRACT AMOUNT: 174 0
Page 2 of 3
CHANGES IN SCHEDULE:
Due to a desire to allow the farmer to remove sweet corn in the general area of the proposed
drainage swale the late start date is revised to August 19, 2013.
The Milestone Dates and Descriptions are revised as follows:
Milestone 1 Installation and seeding complete for the drainage swale
9/18/13 including the associated 12" dia. storm sewer.
Milestone 2: The following shall be complete (installed, tested and
12/18/13 operational):
& All water main along East Cemetery Road.
a Water main along Williams Blvd from Sta 0+00 to Sta
8+%
0 Ail 24" dia. sanitary sewer.
a 8" dia. sanitary sewer to be directionally drilled to East
Cemetery Road and all other 8"' sanitary sewer within East
Cemetery Road.
a 8" dia. sanitary sewer serving EIB property (as shown on
Sheet F.04 of plans),
® Sanitary sewer lift station.
Milestone 3: All remaining work completed and entire project seeded.
5/16/13
Ricklefs cavating L s Hall & Hak Engineers, Inc.
By: L By:
Title: y. Title:
'2
Date: Date
City of Fairfax, Iowa
BY:
Title-.
Date:
Page 3 of 3