RESOLUTION TO APPROVE CHANGE ORDER NO. 3 FROM �
DAVE SCHMITT CONSTRUCTION COMPANY, INC.
FOR THE KARAL'S, DRAINAGE IMPROVEMENTS PROJECT
WHEREAS, the City Council of Fairfax, Iowa has contracted with Dave Schmitt
Construction Company, Inc. for the Karal's Drainage Improvements Project, within the
corporate limits; and
WHEREAS,Hall and Nall Engineers, Inc.,has recommended approval of Change
Order No. 3 from Dave Schmitt Construction Company, Inc. The current contract amount
is $1.00,797.75. This Change Order No. 3 is an, addition to the contract amount of
$4,1397.00, malting the new contract amount $1.05,694.75 as described below:
ITEM#1: Reinforcing Steel for Concrete Flume
In order to alleviate heaving/differential settlement of the concrete flume through freeze
and thaw cycles, the City of Fairfax has requested that wire mesh be added to reinforce
the concrete flume. The type and quantity of wire mesh installed will be 5,900 SF of
W4-D4 @ 4".
The total adjusted Change Order 3 amount is $4,897.00. See Dave Schmitt Construction
Co., Inc. Proposal dated August 28, 2015 (attached) for additional breakdown of costs for
this change. The City has requested the heavier option(Dave Schmitt Invoice Item 92) as
shown on the attached proposal.
Original Contract Amount: $106,32.7.00
C.O. #1, Item 1 ($7,362.50)
C.O. 42, Item 1 $1,833.25
C.O. #3, Item 1 -- _ $4,897.00
Revised Contract Amount: $105,694.75
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of
Fairfax, Iowa, to approve Change Order No, 3 Dave Schmitt Construction Company, Inc.
for the Karal's Drainage Improvements Project.
IBE IT FURTHER RESOLVED, 'by the Fairfax City Council of the C:,ity, of
Fairfax, Iowa, that the Mayor and City Clerk/Treasurer are hereby authorized and directed
to execute said resolution.
Passed and approved this 8th day of September, 2015.
AYES: Beer,Frieden, Otto,Magers, and Wainwright cam.
NAYS: None CIZ :..
`IL ad 1Y 4
I 4®�
.r
a
Jason 1�46e Mayor M ,A
ATTEST:
Cyny is Stimson, City Clerk/Treasurer
i'
I
CHANGE ORDER NO. 3
PROJECT: KARAL'S ADDITION DRAINAGE IMPROVEMENTS
DATE: September 1,2015
CONTRACTOR: Dave Schmitt Construction Company, Inc.
Cedar Rapids, Iowa
ORIGINAL
CONTRACT AMOUNT: $ 106,327.00
ORIGINAL CONTRACT
COMPLETION DATE: October 2,2015
ITEM#1: Reinforcing Steel for Concrete Flume
In ordeC to alleviate heaving I differential settlement of the concrete flume through freeze and thaw cycles,
the City of Fairfax has requested that wire mesh be added to reinforce the:concreie flume. The type and
quantity of wire mesh installed vAll be 5,900 SF of W4-D4 @ 4`.
The total adjusted Change (brier 3 amount is$4,897.00, See Dave Schmitt Constructlon Co., Inc.
Proposal dated August 28, 2015(attached)for additional breakdown of costs for this chwige. The City
has requested the heavier option(Dave Schmitt Invoice 111:ei�n ##2)as shorn on the attacheA proposal..
Original Contract Amount: $106,327.00
C,O.#1, Item 1 ($7,362.50)
C.Q.#2, Item 1 $1,833.25
G.C.#3 Item 1 14 8'07.0£1:
Revised Contract Amount: $105,594.75
Dave Schmitt Construction Company, Inc. Hall &HaII '4.' ers I
fay.�;c`� ,� �`�,�.�.....�— By.
Title. r , T .efirt
Date: _ Date:
City of Fairfax, Iowa
,r
f3
y'
Title:
i
Date:
SEWER • TRUCKING • EXCAVATION
WATER • DEMOLITION • GRADINGG
250 50T.H AVS.SM,CEDAR RAPIDS,IowA 52404 (819)355.8669 FAX(319)395-2677 EQUAL OPPQRTuNiTY&TLoyBu
PROPOSAL: EARTHWORK
Froin: Dave Schmitt Construction Co., Inc, Project: B-15-143JJP
Description: KARAL'S DRAINAGE* G.O. RFQUES
250 50th Avenue S.W. ##3
Cedar Rapids, IA 52404 Bid Location: F'AIRFAX
Phone: 319-365-8669 Bid Date; 812812015
Fax: 319-365-2677
To: HALL & HALL ENGINEERS
ITEM DESCRIPTION BID QTY U/M UNIT BID AMOUNT
01 W2 @ 6"WIRE MESH 5,900,000 SF 0.420 $2,478.00
02. W4-D4 @ 4" WIRE MESH 5,900.000 SF= 0.830 $4,897-00
TOTAL BID:
8128/20115 Dave Schmitt Construction Co., Inc_