HomeMy WebLinkAboutRESOLUTION NO. 2015-75 RESOLUTION NO. 2015-75 i RESOLUTION TO APPROVE CHANGE ORDER NO. 3 FROM � DAVE SCHMITT CONSTRUCTION COMPANY, INC. FOR THE KARAL'S, DRAINAGE IMPROVEMENTS PROJECT WHEREAS, the City Council of Fairfax, Iowa has contracted with Dave Schmitt Construction Company, Inc. for the Karal's Drainage Improvements Project, within the corporate limits; and WHEREAS,Hall and Nall Engineers, Inc.,has recommended approval of Change Order No. 3 from Dave Schmitt Construction Company, Inc. The current contract amount is $1.00,797.75. This Change Order No. 3 is an, addition to the contract amount of $4,1397.00, malting the new contract amount $1.05,694.75 as described below: ITEM#1: Reinforcing Steel for Concrete Flume In order to alleviate heaving/differential settlement of the concrete flume through freeze and thaw cycles, the City of Fairfax has requested that wire mesh be added to reinforce the concrete flume. The type and quantity of wire mesh installed will be 5,900 SF of W4-D4 @ 4". The total adjusted Change Order 3 amount is $4,897.00. See Dave Schmitt Construction Co., Inc. Proposal dated August 28, 2015 (attached) for additional breakdown of costs for this change. The City has requested the heavier option(Dave Schmitt Invoice Item 92) as shown on the attached proposal. Original Contract Amount: $106,32.7.00 C.O. #1, Item 1 ($7,362.50) C.O. 42, Item 1 $1,833.25 C.O. #3, Item 1 -- _ $4,897.00 Revised Contract Amount: $105,694.75 NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Fairfax, Iowa, to approve Change Order No, 3 Dave Schmitt Construction Company, Inc. for the Karal's Drainage Improvements Project. IBE IT FURTHER RESOLVED, 'by the Fairfax City Council of the C:,ity, of Fairfax, Iowa, that the Mayor and City Clerk/Treasurer are hereby authorized and directed to execute said resolution. Passed and approved this 8th day of September, 2015. AYES: Beer,Frieden, Otto,Magers, and Wainwright cam. NAYS: None CIZ :.. `IL ad 1Y 4 I 4®� .r a Jason 1�46e Mayor M ,A ATTEST: Cyny is Stimson, City Clerk/Treasurer i' I CHANGE ORDER NO. 3 PROJECT: KARAL'S ADDITION DRAINAGE IMPROVEMENTS DATE: September 1,2015 CONTRACTOR: Dave Schmitt Construction Company, Inc. Cedar Rapids, Iowa ORIGINAL CONTRACT AMOUNT: $ 106,327.00 ORIGINAL CONTRACT COMPLETION DATE: October 2,2015 ITEM#1: Reinforcing Steel for Concrete Flume In ordeC to alleviate heaving I differential settlement of the concrete flume through freeze and thaw cycles, the City of Fairfax has requested that wire mesh be added to reinforce the:concreie flume. The type and quantity of wire mesh installed vAll be 5,900 SF of W4-D4 @ 4`. The total adjusted Change (brier 3 amount is$4,897.00, See Dave Schmitt Constructlon Co., Inc. Proposal dated August 28, 2015(attached)for additional breakdown of costs for this chwige. The City has requested the heavier option(Dave Schmitt Invoice 111:ei�n ##2)as shorn on the attacheA proposal.. Original Contract Amount: $106,327.00 C,O.#1, Item 1 ($7,362.50) C.Q.#2, Item 1 $1,833.25 G.C.#3 Item 1 14 8'07.0£1: Revised Contract Amount: $105,594.75 Dave Schmitt Construction Company, Inc. Hall &HaII '4.' ers I fay.�;c`� ,� �`�,�.�.....�— By. Title. r , T .efirt Date: _ Date: City of Fairfax, Iowa ,r f3 y' Title: i Date: SEWER • TRUCKING • EXCAVATION WATER • DEMOLITION • GRADINGG 250 50T.H AVS.SM,CEDAR RAPIDS,IowA 52404 (819)355.8669 FAX(319)395-2677 EQUAL OPPQRTuNiTY&TLoyBu PROPOSAL: EARTHWORK Froin: Dave Schmitt Construction Co., Inc, Project: B-15-143JJP Description: KARAL'S DRAINAGE* G.O. RFQUES 250 50th Avenue S.W. ##3 Cedar Rapids, IA 52404 Bid Location: F'AIRFAX Phone: 319-365-8669 Bid Date; 812812015 Fax: 319-365-2677 To: HALL & HALL ENGINEERS ITEM DESCRIPTION BID QTY U/M UNIT BID AMOUNT 01 W2 @ 6"WIRE MESH 5,900,000 SF 0.420 $2,478.00 02. W4-D4 @ 4" WIRE MESH 5,900.000 SF= 0.830 $4,897-00 TOTAL BID: 8128/20115 Dave Schmitt Construction Co., Inc_