HomeMy WebLinkAboutRESOLUTION NO. 2016-54 RESOLUTION NO. 2016-54 RESOLUTION TO APPROVE CHANGE ORDER NO. 2 FROM RATHJE CONSTRUCTION, CO. FOR THE PHASE 4 WATER MAIN AND VANDERBILT PAVEMENT RECONSTRUCTION PROJECT IN THE CITY OF FAIRFAX, LINN COUNTY, IOWA WHEREAS, the City Council of Fairfax, Iowa has contracted with Rathje Construction Co. for the Phase 4 Water Main and Vanderbilt Street Reconstruction Project within the corporate limits; and WHEREAS, Hall and Hall Engineers, Inc., has recommended approval of Change Order#2 as described below: ORIGINAL CONTRACT AMOUNT: $ 752,644.32 ORIGINAL CONTRACT COMPLETION DATE: 85 Working Days ITEM #1: Add 20 SY of Aggregate Driveway Removal (Line Item 10) to the Project Quantities ITEM#2: Add 180 Lf of 8" Dia. PVC Water Main (C-900) (Line Item 43)to the Project Quantities ITEM #3: Add two (2) Water Services (Line Item 46) to the Project Quantities ITEM #4: Add two (2)Water Services (Line Item 48) to the Project Quantities ITEM #5: Additional Disinfection and Hydrostatic Testing (Line Item 50) ITEM #6: Add 20 SY of Aggregate Surfacing for Driveways (Line Item 64)to the Project Quantities ITEM #7 Connections to Existing Water Main (2 Additional Occurrences) ITEM #8 Additional Water Main Fittings (45° MJ Bends) ITEM #9 Add three (3)Working Days to the total project time to allow for completion of this portion of the work During water main installation along Vanderbilt Street, it was discovered that the existing water main, previously believed to be 8" in diameter, was actually 4" water main. Potholing was completed to confirm that this 4" section runs from station 4+00 to the original end of water main replacement location at station 5+80. Water main south of this section was confirmed to be 8" PVC. This change order is for continuing the new 8" PVC water main from the original end location of station 5+80 until the anticipated tie in location near station 4+00. Additional work will include the installation of 4 additional water services, and the removal and replacement of an aggregate driveway disturbed to trench in this water main. An allowance of three (3) additional working days will be granted to the Contractor to perform this work, which will apply to any milestone, incentive, disincentive, or liquidated damages payments. Please see the attached revised Plan Sheet E.01 for a visual representation of this additional work, and the attached Change Order Request Form from Rathje Construction. • Line Item 10, "Removal of Existing Driveway (Aggregate)": 20 SY @ $3.00/ SY = $60.00 • Line item 43, "8" Dia. PVC Water Main (C-900)": 180 LF @ $29.25/ LF = $5,265.00 • Line Item 46, "Water Services, 1" (Plastic) Including Tracer Wire and Removal, Disposal, and Replacement of Existing Curb Stop and Box": 2 EA @ $1,175.00 / EA = $2,350.00 • Line Item 48, "Water Services (Directional Drill), 1" (Plastic) Including Tracer Wire and Removal, Disposal, and Replacement of Existing Curb Stop and Box": 2 EA @ $1,675.00 / EA= $3,350.00 • Line Item 50, "Disinfection and Hydrostatic Testing": 1 EA @ $100.00 EA= $100.00 • Line Item 64, "Aggregate Surfacing for Driveways": 20 SY @ 15.70/ SY = $314.00 • Connections to Existing Water Main 1 EA @ $2,750.00 / EA= $2,750.00 • Additional Water Main Fittings (45' MJ Bends) 2 EA @ $425.00 / EA = $850.00 • Three (3)Additional Working Days to complete this work: $0.00 The total adjusted Change Order 2 amount is($15,039.00). Original Contract Amount: $ 752,644.32 C.O. #1 ($386.50) C.O. #2 $15,039.00 Revised Contract Amount: $767,296.82 NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Fairfax, Iowa, to approve Change Order No. 2 from Rathje Construction Co. for the Phase 4 Water Main and Vanderbilt Street Reconstruction Project for an additional $15,039.00 making the contract amount $767,296.82. BE IT FURTHER RESOLVED, by the Fairfax City Council of the City of Fairfax, Iowa, that the Mayor and City Clerk/Treasurer are hereby authorized and directed to execute said resolution. Passed and approved this 31 st day of May 2016. AYES: Beer, Daly, Kell, Volk, and Wainwrig t NAYS: None Marianne Wainwright, yor Pro Tempore ATTEST: w , 04 �n C n is K. Stimson, City Clerk/Treasurer •1% k o , ea a Y' - CHANGE ORDER NO. 2 PROJECT: PHASE 4 WATER MAIN AND VANDERBILT STREET RECONSTRUCTION DATE: May 27, 2016 CONTRACTOR: Rathje Construction Company, Inc. Cedar Rapids, Iowa ORIGINAL CONTRACT AMOUNT: $ 752,644.32 ORIGINAL CONTRACT COMPLETION DATE: 85 Working Days ITEM#1: Add 20 SY of Aggregate Driveway Removal (Line Item 10)to the Project Quantities ITEM#2: Add 180 Lf of 8" Dia. PVC Water Main (C-900) (Line Item 43)to the Project Quantities ITEM#3: Add two(2)Water Services (Line Item 46)to the Project Quantities ITEM#4: Add two(2)Water Services (Line Item 48)to the Project Quantities ITEM#5: Additional Disinfection and Hydrostatic Testing (Line Item 50) ITEM#6: Add 20 SY of Aggregate Surfacing for Driveways (Line Item 64)to the Project Quantities ITEM#7 Connections to Existing Water Main (2 Additional Occurrences) ITEM#8 Additional Water Main Fittings(450 MJ Bends) ITEM #9 Add three (3)Working Days to the total project time to allow for completion of this portion of the work During water main installation along Vanderbilt Street, it was discovered that the existing water main, previously believed to be 8" in diameter, was actually 4"water main. Potholing was completed to confirm that this 4" section runs from station 4+00 to the original end of water main replacement location at station 5+80. Water main south of this section was confirmed to be 8" PVC. This change order is for continuing the new 8" PVC water main from the original end location of station 5+80 until the anticipated tie in location near station 4+00. Additional work will include the installation of 4 additional water services, and the removal and replacement of an aggregate driveway disturbed to trench in this water main. An allowance of three (3) additional working days will be granted to the Contractor to perform this work, which will apply to any milestone, incentive, disincentive, or liquidated damages payments. Please see the attached revised Plan Sheet E.01 for a visual representation of this additional work, and the attached Change Order Request Form from Rathje Construction. • Line Item 10, "Removal of Existing Driveway (Aggregate)": 20 SY @$3.00/SY= $60.00 • Line item 43, "8" Dia. PVC Water Main (C-900)": 180 LF @$29.25/ LF= $5,265.00 • Line Item 46, "Water Services, 1" (Plastic) Including Tracer Wire and Removal, Disposal, and Replacement of Existing Curb Stop and Box": 2 EA @ $1,175.00/EA= $2,350.00 • Line Item 48, "Water Services (Directional Drill), 1" (Plastic) Including Tracer Wire and Removal, Disposal, and Replacement of Existing Curb Stop and Box": 2 EA @$1,675.00/EA= $3,350.00 • Line Item 50, "Disinfection and Hydrostatic Testing": 1 EA @$100.00 EA= $100.00 • Line Item 64, "Aggregate Surfacing for Driveways": 20 SY @ 15.70/SY= $314.00 • Connections to Existing Water Main 1 EA @$2,750.00/EA= $2,750.00 • Additional Water Main Fittings (45° MJ Bends) 2 EA @ $425.00/EA= $850.00 • Three(3)Additional Working Days to complete this work: $0.00 The total adjusted Change Order 2 amount is($15,039.00). Original Contract Amount: $752,644.32 C.O. #1 ($386.50) C.O,#2 L10-9.00 Revised Contract Amount: $767,296.82 Rathje Constructpn Company Hall & Hall Engineers, l Title: f A-?' /►1 gna e: A4 efrir Date: z5/ 3114. Date: 31 _ City o ax Iowa ; By: Title: Alowvvf ) 111 )0 Date: ': Ol 305 44th Street P.O. Box 408 Marion, I.A. 52302 Office (319)377-3179 • Fax (319)377-3827 Date: May 26,2016 Page 1 of 1 To: City of Fairfax Project: Ph.4 Water Main Replacement& c/o Mr.Joel Gross, PE Vanderbilt St. Paving Reconstruction Hall&Hall Engineers Fairfax, Iowa Re: COR-2 Rathje#: 6651 Additional Water Main on Vanderbilt St. Joel, Per our discussion on site I would like to request the fallowing items be added to your draft Change Order#2 on the Vanderbilt St. Improvement project. Est.Qty. Units Unit Price Extended Price COR2-a Additional Disinfection&Hydrostatic Testing 1.00 LS $ 100.00 $ 100.00 COR2-b Connection to existing Water Main 1.00 Ea. $ 2,750.00 $ 2,750.00 COR2-c Additional Water Main Fittings(45°MJ Bends) 2.00 Ea. $ 425.00 $ 850.00 Please call if you have any questions. Respectfully, Tim Williams —� 4t � - - - O 4f i EXISTING 6"(IA w N WATER MAIN TO1-1 �� r� aC'ws kN i&� _ o Z 1 BE CAPPED AND � 1 p a• (� " EXISTING 8"DIA CONNECT � i PT � Dido• Py �s''� �` � �`; �''� , ABANDONED IN MAIN(TO CONNECT N 0 20 40 C �+ '� �Td PROPOSED) D m N PLACE} SCALE 1"--40' ut �� Z 4A*i�• o oPROPOSED r , l C m r m 8"DIA WATER D •. mz �, MAIN PROPOSED 8" CONNECT �v%nt G'( rXts t GATE VALVE 4 LF OF 01"1"SERVICE ' t S prRi t !!! s t N � #`� � f, S � REMOVE EXISTING ,s� � � �."+"• � �,.�. -3e�-. `� 4+00 . i£ �y I $}, GATE VALVE 1 (RO , ow} 0 f _ .mmk i.. 1 ( t\ VANDERBILT STREET c — — — — I _ Ulu tj {iauaia) _ — G _ v _ I — (OH )` _ _ r I _ { (Row) ' (ROW) Row)-. _ (C):; — .( ( a 5j C NTRACTOR TO -K* ROW ! (R 1 r MA rAIN WEEKEND ,. ® CO NECT CONI�FCT REMOVE,DISPOSE OF,AND = 0T _� lA. as ACCESS TO ALL 55 LFEpF 56 LF OF REPLACE EXISTING CURB m �' G� RIVEWAYS 6PM 1"SERVICE C ( 1"SERVIC STOP.ABANDON EXISTING �< FRIDAY TO 7AM NE[ tl ' WATER SERVICE IN PLACE z MONDAY} z< o AND INSTALL NEW WATER Y =m} ( n m `o o ttt y D`o = As S SERVICE,TYPICAL, CIo mN t D� m N_ z<x 00 m f1 ( E EXISTING GRADE AT PROPOSED WATER MAINvtlt�eP�At` �,O�INE4.T1t'innwe, iN. QYGG'0100 WM• 20 Sy j%vt`t'+* Silk 5}8e 760 760 _. ------------------ ___.._ 75 OVER `. a. "-----._�, EXISTING 8"DI WATER MAIN 120 LF OF F'ROPOSEO as8"DIA VC C-9O WATER MAIN 0 750 BEGIN NEW 8"WATER MAIN.REMOVE EXISTING GATE VALVE. STA 5+79,91 TO STA 7+Op 00 750 EXTEND WATER MAIN OUTSIDE OF PROPOSED TRAIL PAVEMENT INSTALL NEW 8"GATE VALVE. v a C7 r 1. MAINTAIN A MINIMUM OF 5.5 FEET OF COVER OVER THE TOP OF THE PROPOSED WATER MAIN,IN AREAS WHERE THE .� 740 DEPTH OF THE WATER MAIN VARIES,THE DEPTH SHALL BE GREATER THAN 5.5 FEET. 740 / 0 2. THE LOCATION OF THE EXISTING WATER MAIN SHALL BE CONSIDERED APPROXIMATE.IT IS THE RESPONSIBILITY OF THE v CONTRACTOR TO VERIFY THE DEPTH AND LOCATION OF THE EXISTING WATER MAIN,SERVICES AND VALVES. I m 3. ALL PROPOSED WATER SERVICE ASSEMBLIES WILL CONSIST OF I"SERVICE LINE FROM NEW MAIN TO NEWLY INSTALLED WATER SHUT OFF. +r f 4. DRIVEWAY REMOVALS SHALL BE SAW CUT,FULL DEPTH,TO EXISTING DIMENSIONED JOINT UNLESS OTHERWISE NOTED, 730 730 Rf is 1 q) ^'s 'No 1 +50 2+00 2+50 3+00 3+50 4+00 4+50 5+00 5+50 6+00 6+50 7 a DRAWN BY: KLH HALL&HALL ENGINEERS,INC. SHEET CHECKED BY: SRW cit Of ,.- r.uaaawa ..r asyu PHASE 4 WATER MAIN REPLACEMENT AND Y # APPROVED BY: JDG 11-BOYSON ROAD,HIAWATHA,IOWA 52233 VANDERBILT STREET PAVING RECONSTRUCTION VANDERBILT STREET DATE, 7/28/2015 FAIRFAX PHONE.(318)362-9549 FAX.(319)3827685 WATER MAIN PLAN AND PROFILE E.01 la CIVIL ENGINEERING•LANDSCAPE ARCHITECTURE IN THE CITY OF FAIRFAX, LIMN COUNTY, IOWA FIELD BOOK: FF5 NO, REVISION DESCRIPTION APPROVED DATE LAND SURVEYING.LAND DEVELOPMENT PLANNING w hallmg wm a SCALE: 1"=40'H 1"=tO'V PROJECT NO:6950-14-01 CHANGE ORDER NO. 2 PROJECT: PHASE 4 WATER MAIN AND VANDERBILT STREET RECONSTRUCTION DATE: May 27, 2016 CONTRACTOR: Rathje Construction Company, Inc. Cedar Rapids, Iowa ORIGINAL CONTRACT AMOUNT: $ 752,644.32 ORIGINAL CONTRACT COMPLETION DATE: 85 Working Days ITEM #1: Add 20 SY of Aggregate Driveway Removal (Line Item 10) to the Project Quantities ITEM #2: Add 180 Lf of 8" Dia. PVC Water Main (C-900) (Line Item 43) to the Project Quantities ITEM #3: Add two (2) Water Services (Line Item 46) to the Project Quantities ITEM #4: Add two (2) Water Services (Line Item 48) to the Project Quantities ITEM #5: Additional Disinfection and Hydrostatic Testing (Line Item 50) ITEM #6: Add 20 SY of Aggregate Surfacing for Driveways (Line Item 64) to the Project Quantities ITEM #7 Connections to Existing Water Main (2 Additional Occurrences) ITEM #8 Additional Water Main Fittings (450 MJ Bends) ITEM #9 Add three (3) Working Days to the total project time to allow for completion of this portion of the work During water main installation along Vanderbilt Street, it was discovered that the existing water main, previously believed to be 8" in diameter, was actually 4" water main. Potholing was completed to confirm that this 4" section runs from station 4+00 to the original end of water main replacement location at station 5+80. Water main south of this section was confirmed to be 8" PVC. This change order is for continuing the new 8" PVC water main from the original end location of station 5+80 until the anticipated tie in location near station 4+00. Additional work will include the installation of 4 additional water services, and the removal and replacement of an aggregate driveway disturbed to trench in this water main. An allowance of three (3) additional working days will be granted to the Contractor to perform this work, which will apply to any milestone, incentive, disincentive, or liquidated damages payments. Please see the attached revised Plan Sheet E.01 for a visual representation of this additional work, and the attached Change Order Request Form from Rathje Construction. • Line Item 10, "Removal of Existing Driveway (Aggregate)": 20 SY @ $3.00 / SY = $60.00 • Line item 43, "8" Dia. PVC Water Main (C-900)": 180 LF @ $29.25 / LF = $5,265.00 • Line Item 46, "Water Services, 1" (Plastic) Including Tracer Wire and Removal, Disposal, and Replacement of Existing Curb Stop and Box": 2 EA @ $1,175.00 / EA = $2,350.00 • Line Item 48, "Water Services (Directional Drill), 1" (Plastic) Including Tracer Wire and Removal, Disposal, and Replacement of Existing Curb Stop and Box": 2 EA @ $1,675.00 / EA = $3,350.00 • Line Item 50, "Disinfection and Hydrostatic Testing": 1 EA @ $100.00 EA = $100.00 • Line Item 64, "Aggregate Surfacing for Driveways": 20 SY @ 15.70 / SY = $314.00 • Connections to Existing Water Main 1 EA @ $2,750.00 / EA = $2,750.00 • Additional Water Main Fittings (45° MJ Bends) 2 EA @ $425.00 / EA = $850.00 • Three (3) Additional Working Days to complete this work: $0.00 The total adjusted Change Order 2 amount is ($15,039.00). Original Contract Amount: $ 752,644.32 C.O. #1 ($386.50) C.0, #2 $15,039.00 Revised Contract Amount: Rathje Constructip Company Hall & H 1 Engi By: By: , Title:/ _ M�� e� .. _ Title: ?4oz-e it s� Date:�f/G _ _ Date: 1 v C N. Ti Date: f 0 2;kU�� $767,296.82 0 305 4411M Street • P.O. Bax 408 • Marion, iA 52302 Office (319)377-317$ - Fax (319)377--3827 Date: May 26, 2016 To: City of Fairfax c/o Mr. Joel Gross, PE Hall & Hall Engineers Re: COR -2 Additional Water Main on Vanderbilt St. Page 1 of 1 Project: Ph. 4 Water Main Replacement & Vanderbilt St. Paving Reconstruction Fairfax, Iowa Rathje #: 6651 Joel, Per our discussion on site I would like to request the following items be added to your draft Change Order #2 on the Vanderbilt St. Improvement project. Please call if you have any questions. Respectfully, Tim Williams -- Est. Qty. Units Unit Price Extended Price COR2-a Additional Disinfection & Hydrostatic Testing 1.00 LS $ 100.00 $ 100.00 COR2-b Connection to existing Water Main 1.00 Ea. $ 2,750.00 $ 2,750.00 COR2-c Additional Water Main Fittings (450 MJ Bends) 2.00 Ea. $ 425.00 $ 850.00 Please call if you have any questions. Respectfully, Tim Williams -- `I EXISTING 6" DIA Z WATER MAIN (TO " IOU a N arN$}�cM � {' � c� � z a• h (, ^ ^"^'�" EXISTING 8" DIA WATER t BE CAPPED AND yiA•_���`'t ABANDONED IN z^�Y 6� MAIN (TO CONNECT `{{ �'00 TO PROPOSED) a - w wm N<� ' PLACE} • rrr z;00 PROPOSED Cn rq 0 o m S�\ 8" DIA WATER rq MAIN z PROPOSED 8" CONNECT t COriRi Gt �.x1S771�0 4 , ti a t 1 F1f GATE VALVEj 4 LF OF ` $~ �IA - PVC, VJr c �y 1" SERVICEJ:t ji 11 ,,p� - `3 i •" REMOVE EXISTING �'W • 3* s roK �•�e.i� _ ` I GATE VALVE I s, ci ..,,..� /..�. � .,.... .... ....._ FSE ._ tt i i ..-•. � I I I 74 (WO (W } f-- - i VANDERBILT STREET- �-' ( —ONE)— — — — — — — — — — — J M} I { _ (ROW) ROS Ai(}<: - - (,}- -=( _ Q (Rii I C NTRACTOft TO re i" ` ti P Ri1tA3 ( (R w w- MA TAftJ WEEKEND ° _ `� CON ECT CO NECT REMOVE, DISPOSE OF,AND ACCESS TO ALL 55 LF.OF REPLACE EXISTING CURB s s tti� r� © 56 L OF 4 RIVEWAYS (6PM � 1" SERVIG 1" SERVICE STOP. ABANDON EXISTING FRIDAY TO 7AMN c r y �. WATER SERVICE IN PLACE n z �� MONDAY) z o <o IMM7 `o \ ` AND INSTALL NEW WATER N ri" N m �S Dao _ SERVICE, TYPICAL. ,.Qo O mN D41 om\ mN ZO<2 '=Z DQ, EXISTING GRADE AT Qh % 1 PROPOSED WATER MAIN G''Ot�� s7 C o ------------ 760 — 04 -----------._______..____-._-_._____.___._ 5.5' MINIMUM COVER EXISTING H" DIA WATER MAIN 120.1_F OF PROPOSED � �-�.....�, - _ ---"-'-•-_~•.�- BEGIN NEW 8" WATER MAIN. REMOVE EXISTING GATE VALVE. STA DIA PVC C -90p WAtE,3 MAIN 75O $-79,91 T8"O STA 7+t30.00 EXTEND WATER MAIN OUTSIDE OF PROPOSED TRAIL PAVEMENT INSTALL NEW 8" GATE VALVE. = COVER OVER THE TOP OF THE PROPOSED WATER MAIN, IN AREAS WHERE THE IE DEPTH SHALL BE GREATER THAN 5.5 FEET. 740 ITER MAIN SHALL BE CONSIDERED APPROXIMATE. IT IS THE RESPONSIBILITY OF THE i� al