HomeMy WebLinkAboutRESOLUTION NO. 2016-89 RESOLUTION NO. 2016-89 RESOLUTION TO APPROVE CHANGE ORDER NO. 1 FROM RATHJE CONSTRUCTION, CO. FOR THE 2016 80th STREET WATER MAIN EXTENSION PROJECT IN THE CITY OF FAIRFAX, LINN COUNTY,IOWA WHEREAS, the City Council of Fairfax, Iowa has contracted with Rathje Construction Co. for the 2016 80th Street Water Main Extension Project within the corporate limits; and WHEREAS,Hall and Hall Engineers, Inc., has recommended approval of Change Order#1 as described below: ORIGINAL CONTRACT AMOUNT: $ 323,871.00 ORIGINAL CONTRACT COMPLETION DATE: 30 Working Days ITEM #1: 1,500 SY of Erosion Control Matting ITEM #2: (10) 16' long Silt Sock for Ditch Checks This change order is to add a 12' wide swath of North American Green SC15013N coconut fiber mat to the ditch and silt socks as erosion control checks every 100' between Robson's Farm driveway and Highway 151. The ditch in this area is steep enough and conveys enough water that this additional erosion control during and after seeding is warranted. Prices include supply and installation of materials. Please see the attached Change Order Request from Rathje Construction and Estimate from Stevens Erosion Control,Inc. • Erosion Control Matting— North American Green SC15013N: 1,500 SY @$1.82 I SY= $2,730.00. • Silt Socks for Ditch Checks (16' Long): 10 EA @$39.601 EA= $396.00. One (1) additional Working Day will be added to the count to cover installation time for items implemented under this Change Order. The revised total allowable working days for this project will be 31. The total adjusted Change Order 1 amount is$3,126.00. Original Contract Amount: $ 323,871.00 C.O. #1 $3,126.00 Revised Contract Amount: $326,997.00 NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Fairfax, Iowa, to approve Change Order No. 1 from Rathje Construction Co. for the 2016 801h Street Water Main Extension Project for an additional $3,126.00 making the contract amount $326,997.00. BE IT FURTHER RESOLVED, by the Fairfax City Council of the City of Fairfax, Iowa,that the Mayor and City Clerk/Treasurer are hereby authorized and directed to execute said resolution. Passed and approved this 9th day of August, 2416. AYES: Beer, Kell, Volk, and Wainwright NAYS: None ABSENT: Daly Burnell G. Frieden, Mayor ATTEST: 01 Cyn is K. Stimson, City Clerk/Treasurer tix i sr• ��` '�e uwF CHANGE ORDER NO, i PROJECT: 2016 80" Street Water Main Extension DATE: August 8, 2016 CONTRACTOR: Rathje Construction Co. 305 44th Street P.O. Box 408 Marion, Iowa 52302 ORIGINAL CONTRACT AMOUNT: $ 323,871.00 ORIGINAL CONTRACT COMPLETION DATE: 30 Working Days ITEM #1: 1,500 SY of Erosion Control Matting ITEM#2: (10) 16' long Sift Sock for Ditch Checks This change order is to add a 12' wide swath of North American Green SC15OBN coconut fiber mat to the ditch and silt socks as erosion control checks every 100' between Robson's Farm driveway and Highway 151, The ditch in this area is steep enough and conveys enough water that this additional erosion control during and after seeding is warranted. Prices include supply and installation of materials. Please see the attached Change Order Request from Rathje Construction and Estimate from Stevens Erosion Control, Inc. • Erosion Control Matting — North American Green SC1506N: 1,500 SY @ $1.82 I SY= $2,730.00. a Silt Socks for Ditch Checks (16' Long): 10 EA @ $39.601 EA : $396.00. One (1) additional Working Day will be added to the count to cover installation time for items implemented under this Change Order, The revised total allowable working days for this project will be 31. The total adjusted Change Order 1 amount is $3,126.00, Original! Contract Amount: $ 323,871.00 C,O, #1 3,126.00 Revised Contract Amount: $326,997.00 Rathje Cons .uetion Co. Hall & Hall ngine Y� Title: Titl Date: • Date: City of Fairfax Iowa By: Title. Date: _