HomeMy WebLinkAboutRESOLUTION NO. 2016-107 RESOLUTION NO. 2016-107
RESOLUTION APPROVING THE PHASE 3 STREET PAVING,
BEVERLY ROAD TRAIL PAVING AND STORM SEWER PLAN OF
IMPROVEMENTS AND STORM SEWER DESIGN
CALCULATIONS FOR HEARTLAND HEIGHTS FIRST ADDITION
IN THE CITY OF FAIRFAX, LINN COUNTY, IOWA
WHEREAS, a Plan of improvements dated September 27, 2016, has been
submitted to the City of Fairfax, Iowa, from Iowa Lot Development Co. and Nick.Bettis,
PE., with HB K Engineering,, L.L.C. for the Phase 3 Street Paving, Beverly Road, "frail
Paving and Storm Sewer Plan of Improvements, and Storm Sewer Design Calculations for
Heartland Heights First Addition in the City of Fairfax, Linn County, Iowa; and
WHEREAS, the Developers have requested variances from the design standards
as part of these Phase 3 Street Paving, Beverly Road Trail Paving and Storm Sewer Plan
of Improvements for Heartland Heights First Addition in the City of Fairfax,Linn County,
Iowa for the following: 1.)the vertical curves in the south sections of Eagleview Drive and
Bridgewood Drive; 2.) the vertical curve located at the east end of Beverly Road near 84th
Street; and for 3)the water quality volume that is to be located upstream of the wet bottom
detention pond to be reduced to 20% of the design water quality volume.
WHEREAS, Hall and Hall Engineers, Inc. has reviewed said Phase 3 Street
Paving, Beverly Road Trail Paving and Storm Sewer Plan of Improvements, and Storm
Sewer Design Calculations for Heartland Heights First Addition in the City of Fairfax,
Linn County, Iowa and has recommended approval of the Phase 3 Street Paving, Beverly
Road Trail Paving and Storm Sewer Plan of Improvements, and Storm Sewer Design
Calculations for Heartland Heights First Addition in the City of Fairfax,Linn County,Iowa
with the following conditions:
I. That all outstanding comments regarding the water main plan of improvements as
detailed, in the Review Letter dated Sept 27, 2016 are addressed prior to any
Storm Sewer construction at Heartland Heights First Addition,
2. Testing on the street subgrade and street paving, and verification of the granular
subbase depth shall be completed prior to beginning of the next step in
constructing the streets, These shall be completed per the Cedar Rapids
Metropolitan Area Standard Specifications,
3. That prior to performing any improvements on the storm sewer,the developer
shall contact the City of Fairfax and Hall and Hall Engineers, Inc. to coordinate
construction observation on these improvements.
4. That prior to performing any improvements on,the storm sewer system within the
public right-of-way where fill.is being placed, the developer shall submit
satisfactory compaction test results for the fill material placed within the right-of-
way.
5. That prior to performing any improvements on the storm sewer system within the
areas of the right-of-way where significant fill is being placed, settlement of this
fill material and the native sub-materials shall be minimized.
6. That prior to the installation of any storm sewer or storm sewer intakes located in,
surrounding, and/or near the existing high pressure gas line and, gas easement,
and prior to the installation of Beverly Road located in, surrounding, and/or near
the existing high pressure gas line and gas easement, the Developers and
MidAmerican Energy shall determine where this easement is/or shall be located,
and MidAmerican Energy provides the City of Fairfax with written approval of
these plan of improvements.
7. That prior to the installation of the 54" diameter storm sewer (located between
proposed Lots 85 and 86) from the outlet to the water quality feature to Intake A2,
the water quality feature at this outlet is designed and approved.
8. That prior to the acceptance of the public improvements, the developer shall
provide the City of Fairfax with GIS As-Built drawings of the public
improvements.
9. That prior to the acceptance of the public improvements,the developer shall
provide the City with a 4-year performance /maintenance bond covering all the
public improvements within the proposed development. An engineer's estimate
for these public improvements shall be submitted with this bond to determine the
amount of the bond.
10. That prior to the acceptance of the public improvements,the developer shall
complete a final plat for Heartland Heights First Addition, including a
development agreement to be recorded with this final plat.
NOW, THEREFORE BE 1T RESOLVED, that the City Council of Fairfax, Iowa,
approves the requested variances from the design standards as part of the Phase 3 Street
Paving, Beverly Road Trail Paving and Storm Sewer Plan of Improvements for Heartland
Heights First Addition in the City of Fairfax, Linn County, Iowa for the following: 1.) the
vertical curves in the south sections of Eagleview Drive and Bridgewood Drive; 2.) the
vertical curve located at the east end of Beverly Road near 80"' Street; and for 3.)the water
quality volume that is to be located upstream of the wet bottom detention pond to be
reduced to 20% of the design water quality volume, as part of the,
NOW, T1,1EREFORE, BE IT RESOLVED, that the City Council of Fairfax, Iowa,
approves the Phase 3 Street Paving, Beverly Road Trail Paving and Storm Sewer Plan of
Improvements, and the Storm Sewer Design Calculations for Heartland Heights First
Addition in the City of Fairfax, Linn County, Iowa with the conditions as listed above and
submitted by Hall and Hall Engineers, Inc.
BE IT FURTHER RESOLVED,by the City Council of Fairfax,Iowa,that the Mayor
and the City Clerk are hereby authorized and directed to execute said Resolution.
Passed and approved this 271s day of September 2016.
AYES: Beer, Daly, Kell, Volk, and Wainwright
ISBume�11G. Frieden,�Mayor ��
ATTEST:
CL
Clerk/Treasurer
J(- rla' 'S'tinISOn, City -4
01
1)-�64
0)